Attachment D Construction Manangement Plan · 132003.221152.5

Attached to the e-mail 132003.221152.5 - Response to further information - Part 2.

of 6

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
          Manual material handling will be employed throughout the construction
           to minimise construction activities and impact on the site, especially
           existing vegetation
          All construction and materials handling will be undertaken beneath the
           tree canopy thereby avoiding potential damage to the canopy
          All trees within the work area will be fenced during construction
          The Builder is to utilise where possible all trades and workers who
           were involved in building the residence on No. 12 Park Road. This will
           ensure that all workers understand the sensitivity of the site, the
           importance of preserving the vegetation and the need to minimise
           noise, dust and other building activity impacts on adjacent home
           owners and the public.
          The working area will be minimised to protect any significant
           vegetation
          The smallest possible machine to install screw piles will be utilised to
           minimise impact on vegetation and slope stability

1.8 REMOVAL OF BUILDING WASTE

   Building waste will be collected in a garbage trailer or light truck situated
   adjacent to the garage of No. 10 Park Road. Sand spoil will be lowered daily
   from the terrace platform to the garbage trailer or light truck located adjacent
   to the garage of No.10 Park Road.

1.9 EROSION AND SEDIMENT CONTROL

   Erosion and Sediment Control is considered for both work areas as
   summarised below:

          The driveway to park Road will require silt fences to be installed to the
           perimeter of the works. Sand bags will be placed in the gutters during
           excavation and concreting to prevent runoff into the Council
           stormwater system.
          Erosion and Sediment Control for the proposed terrace will require a
           silt fence to the perimeter of the proposed footing excavation.
          The permanent stormwater drainage system will be connected to the
           Council system as an early works operation. This will be done to
           prevent any concentrations of runoff discharging onto the sand slope.

1.10   TRAFFIC MANAGEMENT

       The first operation will be the installation of the screw piles and excavation
       of footings. During this stage the builder shall engage the services of a
       traffic management company to ensure there is no interference to the
       general traffic using Park Road. Traffic controllers will be required to be

Used in these records

About this file

File size
871 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment D Construction Manangement Plan.pdf · 871 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.