                               Standard Guidelines MD-03/12

When considering Works, either on Energex easements or in the vicinity of Energex
assets, please be aware of the following general conditions:

   Satisfactory clearance from your proposed structure to the existing (and/or future)
    electricity wires must be maintained in accordance with the Electrical Safety
    Regulations 2013.

   All previous conditions must be adhered to and Energex may, at its discretion, audit
    the finished development to check that it conforms to the conditions of the
    development.

   Detailed civil design drawings showing any proposed cut and fill levels on the
    easement and the location of the Energex assets in relation to the proposed
    development must be approved by Energex before any works can commence on
    site.

   No civil works are to occur within 5 metres of any part of an Energex Structure
    (e.g.- tower base, pole or stay) without Energex approval.

   If the minimum 5m horizontal separation to the Energex structure cannot be
    achieved, the Developer must consult Energex with regards to allowable
    construction methods. This may include full depth shoring of the excavation sides
    for a minimum of 5 metres either side of the structure.

   Any excavations deeper than 5m must have a minimum horizontal separation from
    the excavation to any tower, base or pole at least equal to the excavation depth.
    The excavation is not to be left open overnight and backfill is to be compacted in
    150mm layers in the immediate vicinity of the structure.

   10 metres clear access must be provided around all towers and pole structures
    after the completion of any works on the easement.

   Natural ground level on the easement should not be disturbed without Energex
    approval.

   Final ground levels should slope gently to the edge of the easement, surrounding
    area or kerb such that pooling of water on the easement is avoided and conductor
    ground clearances are not decreased.

   Stockpiling of spoil on the easement is prohibited.

   Lighting structures are not permitted in the easement without prior written consent
    of Energex. Lighting designs for proposed developments (e.g. road, carparks etc)
    on the easement are likely to require reduced height structures. Please submit
    detailed design to Energex for approval. These drawings must clearly show the
    following;
     Proposed height of the lighting structures and the ground level at the structure
         base,
     Relative (to lighting structures) ground levels at Energex structures (towers,
         pole etc) either side of the lighting structures, and
     The location of the Energex structures in relation to the proposed lighting
Reference:   HBD 5390549 346062

                         Did you know Energex has a referral website?
     https://www.energex.com.au/home/our-services/connections/development-application-referrals
Log in to download the original file

EGX_PROD_n5390549_28_Eenie_Creek_Road,_Noosaville_Part_of_L3_on_SP246584.pdf · 230 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.