2022-07-12 Planning & Environment Meeting Agenda

of 150

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (26.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA                                       12 JULY 2022


             undertaken by Council’s contractor via rear lift trucks with the trucks collecting 1100
             litre bins.
     43.     The developer must provide waste storage and disposal facilities in accordance with
             Planning Scheme Policy 9 - Waste Management. The facilities must include an
             impervious area, within the site, correctly sized for all refuse and recycling containers
             and suitably screened from public places and neighbouring properties. A bin wash area
             is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket
             trap. The drain outlet must be designed to prevent storm water entry to the sewerage
             system.
     44.     Refuse containers must be provided in accordance with the requirements of the
             Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
             Regulation 2000, for the storage and collection of refuse.
     45.     Storage, disposal and management of solid, liquid and vegetative waste is conducted
             in a safe and ecologically sustainable manner without environmental nuisance. In this
             regard, vegetated waste must be disposed of via a green waste bin or at a local transfer
             station.
B.   Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.


REPORT
A report for this application was presented to Council at the Planning and Environment Committee
on 12 April 2022. The report recommended that the application be refused based on the proposal
not complying with site cover, plot ratio, setbacks and landscaping and the development not being
consistent with the streetscape or the surrounding area.
On 19 April 2022 the applicant stopped the Decision-Making Period until 22 April 2022 and
subsequently extended the Decision-Making Period until 21 July 2022 to allow for an amended
proposal to be considered by Council.
On 26 May 2022 Council officers met with the applicant at which time some agreement was
reached in terms of design changes that would address Council’s concerns. It was generally
agreed to:
•    Increase the setback to the front road boundary from the outermost projection of the building
     so that it is no less than 5m from the boundary. It was noted that the increased setback could
     be increased by a combination of things including:
     o     a relaxation to the rear setback. Pushing the whole development towards the rear
           boundary by 0.5m;
     o     push units 6 & 7 back towards the rear boundary instead of forward by approximately
           0.9m, still retaining the articulation in the back wall of the building;
     o     reduce the depth of the overhang on the front of units 1-4 if necessary to achieve a 5m
           minimum setback.
•    Create small units to increase the small unit numbers and allow the bonus provisions for site
     cover and plot ratio to apply being up to 45% for site cover and 0.5:1 for plot ratio.
•    Provide additional landscape treatment in the rear of the courtyards of Units 1-5 to offset the
     decrease in size. This may involve retaining walls to make the area more useable, with soft
     landscaping along the back.
•    Increase the landscaping in the front of units 1-4 and remove the lightweight screens unless
     they can be pushed back behind the setback area.
The applicant submitted revised plans on 8 June 2022 and it is these plans that form the basis of
the assessment.

                                                                                     Page 75 of 150
Log in to download the original file

2022-07-12 Planning & Environment Meeting Agenda(PDF, 25MB).pdf · 26.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.