Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

2022-07-12 Planning & Environment Meeting Agenda

of 150

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (26.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA                                     12 JULY 2022


          b.    shrubs must have a maximum spacing of 1.5m; and
          c.    ground covers planted between the trees and shrub must achieve a dense
                coverage.
    13.   The development is to provide adequate landscape buffering to protect the character
          of the beachfront, to the reasonable satisfaction of the Manager Development
          Assessment.
    14.   Two 100 litre street trees must be provided within the frontage. The trees must be a
          coastal species in accordance with PSP2 – Landscaping.
    Coastal Protection
    15.   External colours and finishes of the building must comprise of muted/environmental
          tones that blend with the natural environment.
    Pedestrian Access
    16.   A pedestrian access gate must not be installed along the seaward property boundary
          with direct access by residents to the beachfront area not being permitted.
    Geotechnical Stability
    17.   A footing system and erosion protection system must be designed for the proposed
          development to withstand the short-term erosion associated with a 500-year average
          recurrence interval storm event combined with shoreline recession due to sea-level
          rise for 2100 climate change. The short-term erosion associated with a 500-year
          average recurrence interval storm event combined with shoreline recession due to sea-
          level rise for 2100 climate change to be considered for the design as per the
          recommendations of the Royal Haskoing DHV report ‘Report 66 Seaview Terrace,
          Sunshine Beach Coastal Hazards Assessment, reference PA2906-RHD-ZZ-XX-RP-Z-
          0001 dated 3 June 2022.
    18.   The footing system and erosion protection system must in accordance with the works
          detailed in the Tectonic report “Geotechnical Investigation, Proposed residence 66
          Seaview Terrace, Sunshine Beach”, (Reference 21370-001-Rev 1 dated 28 April 2022)
          and other supporting documents referenced in the Tectonic report.
    19.   The design must include the protection of the northern and southern boundaries of the
          site to prevent erosion on neighbouring properties exposing the side boundaries of the
          site to erosion. The minimum extent of the side boundary protection must be
          determined by a line drawn at 28° extending upwards to the west from the base of the
          rear point of the erosion as per the recommendations of Tectonic report “Geotechnical
          Investigation, Proposed residence 66 Seaview Terrace, Sunshine Beach”, reference
          21370-001-Rev 1 dated 28 April 2022.
    20.   The design must be accompanied by certification by a Registered Professional
          Engineer of Queensland (RPEQ) specialising in geotechnical engineering that the
          design is satisfactory and will provide a long-term factor of safety concerning slope
          stability of no less than 1.5.
    21.   Following construction, certification must be supplied to Council by an RPEQ
          specialising in geotechnical engineering that the works have been constructed in
          accordance with the approved design.
    22.   A dilapidation survey shall be carried out of all adjacent properties and structures
          before the commencement of construction of the proposed development on the site.
    23.   Due to the risk of instability on the existing dune slope and the potential for settlement
          of loose sand on the adjacent properties, vibrations must be kept to a minimum and
          must be monitored during the construction of the development. Driven piles (both
          sheet piles and pile footings) are not permitted on the site.


                                                                                   Page 97 of 150
Log in to download the original file

2022-07-12 Planning & Environment Meeting Agenda(PDF, 25MB).pdf · 26.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.