• Lodging a submission: All Reconstruction of Essential Public Assets submissions,
including awarded market prices, must be lodged to Queensland Reconstruction Authority
within nine months (by 31 March) following the financial year in which the relevant disaster
occurred.
• Updating a submission with awarded market price: All requests to update an approved
submission with awarded market prices, must be lodged to Queensland Reconstruction
Authority within nine months (by 31 March) following the financial year in which the relevant
disaster occurred.
• Reporting on works: Monthly progress reports are required throughout delivery.
• Completing works: All Reconstruction of Essential Public Assets works must be completed
within 24 months after the end of the financial year in which the disaster occurred.
• Acquitting approved works and expenditure: Unless otherwise agreed with Queensland
Reconstruction Authority, all Reconstruction of Essential Public Assets acquittal reports and
evidence must be lodged to Queensland Reconstruction Authority within three months of
completing the works.
2
Page 26 of 610
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.