Vegetated Devices
38. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The
approved Operational Works drawings for the stormwater quality treatment system and
detailed life cycle costing of the system must be attached as an addendum to this
document. Records of all maintenance activities undertaken must be kept and made
available to Council upon request.
Rainwater Harvesting
39. Operating rainwater collection tanks must be provided for the development. The tanks
must be provided in accordance with an Operational Works approval and must include in
particular:
(a) the details identified in section 5 of the Site Based Stormwater Quality
Management Plan listed in this Decision Notice
(b) a total tank capacity of 50 000 litres
(c) Deleted.
(d) re-use of harvested rainwater for internal non-potable uses and outdoor uses.
40. Certification must be submitted to Council from a qualified person* which certifies that the
rainwater collection tank and associated reticulation have been installed in accordance
with the requirements of this Decision Notice. *(Refer to Advisory Note)
Easements
41. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property. All easements must be designed in
accordance with the planning scheme and granted at no cost to the Grantee. Where the
Grantee is Council or a service authority, the easement documentation must be in
accordance with the Grantee’s standard easement terms.
42. Draft easement documentation must be submitted to Council for endorsement.
43. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
44. All fill and associated batters must be must be undertaken in accordance with an
Operational Works approval, and contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council.
Damage to Services and Assets
45. Any damage caused to existing services and assets above or below the ground must be
repaired:
(a) where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
(b) where otherwise, upon completion of the works associated with the development.
(c) Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
Page 41 of 112
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.