Table 18—Specific outcomes and probable solutions for the reconfiguring a lot code
Specific outcome Probable solution Applicant response
d) enable the retention and space areas and physical linkages
protection of significant vegetation, to these areas are provided;
wetlands, watercourses, drainage AND
lines and other native habitat S25.3 Open space is provided
areas, their associated buffers and adjacent to watercourses, with
linkages/corridors and natural and roads servicing the linear parkland
cultural features; and and lots located on the opposite
e) be cost effective to maintain41. side of the road to the
watercourse;
AND
S25.4 Public open space has good
connectivity for users via
pedestrian and cycle paths.
O26 Land provided for active S26.1 Active parkland is of a Not applicable.
recreation areas is of a physical compact shape free of irregular The proposed development does
standard and condition suitable for boundaries; not involve the dedication of
the intended uses and is not AND parkland.
subject to physical or other S26.2 Active parkland is located on
constraints including land that is exclusive of—
contamination, environmental or a) flood inundation below the 20%
biophysical constraints or AEP (1:5 year ARI level);
legislative protection that would b) land affected by stormwater or
encumber its use. overland flow discharge from
adjacent allotments;
c) drainage reserves and detention
basins, which cannot be shown to
safely and effectively contribute to
the network of parks and open
space areas;
d) land with a slope, or subject to
cut and fill with a batter slope, that
exceeds a slope of 1 in 67 (15%);
e) areas of land less than 15m
wide, such as access and service
and utility easements;
f) land required to serve primarily
as a buffer area to any existing
development or major transport
corridor; and
g) power easements; AND
S26.3 At least 10% of the total
open space provision for active
parkland is exclusive of flood
inundation below the 1% AEP
(1:100 year ARI level or the
highest recorded flood level,
whichever is the greatest;
AND
S26.4 Recreational facilities
(including playgrounds, pergolas,
barbeques etc.) are setback a
minimum of 30m from the top of
ROL, 2 David Low Way Page 49 August, 2017
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.