Planning Response letter to Council Information Request · MCU18/0015
Attached to the e-mail Response to Information Request (Planning Response & Architectural Plan Series Part 1)MCU18/0015 & RAL18/0001.
Response – In response to Council’s information request, the number of proposed dwelling house
lots has been reduced from 3 to 2. The middle lot which was the closest to the creek has been
removed. The allotments and building envelopes have been amended to provide greater setback
and separation from the high bank of the creekline with a setback of over 40m being achieved to
Lot 2 and a setback of 10m achieved from the building envelope to the creek.
Item 17 – Provide an amended layout which demonstrates the development maintains a wildlife
corridor of a minimum vegetated width of 50m and demonstrate any cantilevering of buildings will
not impact on the minimum vegetated width of 50m.
Response – Included at Attachment 3 is an Environmental Connectivity Plan showing the proposed
green corridor to be maintained through the site and how it will connect with existing tracts of
retained vegetation surrounding the site and ultimately connect to the national park. This plan
shows a minimum setback between buildings of 41m, a maximum setback of 84m and an average
setback of 66m. This corridor is considered ample to cater to Council’s desire to maintain a wildlife
corridor through the site.
Item 18 – Provide a preliminary arborist assessment on the likelihood of the retention of these trees
and provide recommendations to ensure the Hoop Pines flourish in a post development
environment.
Response – Included at Attachment 8 is an Arborist Report which was prepared to assess and
provide recommendations regarding retention of the hoop pines. Several alterations were made
to the proposed development design in response to the arborist assessment including pulling back
of the driveway around the hoop pines and re-direction of the stormwater infrastructure to ensure
such infrastructure is suitably located to minimise impact on the tree’s structural root zone. The
arborist report concludes that retention of the three hoop pines is viable and provides
recommendations that should be adopted as part of any proposed site works. Further detailed
assessment can be undertaken at operational works phase if required.
Item 19 – Clear detail of all of the areas where vegetation is to be removed and disturbed as a
result of the proposed development and associated infrastructure.
P: 07 5452 5207
E: [email protected]
45 First Ave, Mooloolaba Qld 4557
PO Box 1043 Maroochydore Q 4558
Page 7 of 19 townplanningsunshinecoast.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Planning Response letter to Council Information Request.pdfRelated documentApplication case desk ↗
About this file
- File size
- 649 KB (small file)
- File type
No other editions are linked here.