                              c.       Erosion and sediment control works.
                                       * (Refer to Advisory Note)
                      11.     Copies of the approved plans, duly signed by the consultant Registered
                              Professional Engineer of Queensland (RPEQ) must be provided to Council’s
                              Engineering Officer Construction at the “prestart” meeting.
                      12.     A detailed existing condition report and photographs of all frontages of the site
                              including existing footpath, kerb line and road pavement must be completed and
                              submitted to Council prior to the prestart meeting.
                      13.     A condition report including photographs of all existing fences and retaining walls
                              bordering the site and any buildings, structures, pathways, landscaping features
                              etc on adjoining properties that could potentially be impacted on by the proposed
                              earthworks and construction works must be completed and submitted to Council
                              prior to the prestart meeting.
                      14.     A Construction Management Plan must be submitted to Council for approval prior
                              to the prestart meeting and must specifically include/address the following:
                              a.       Traffic Management during all aspects of the construct phase including:
                                       i.        A Traffic Management Control Plan in accordance with Manual of
                                                 Uniform Traffic Control Devices (MUTCD) detailing all temporary
                                                 signage and traffic control measures to be installed prior to
                                                 construction.
                                       ii.       Fencing to the work site during the construction phase to ensure the
                                                 safety of the public and the road users.
                                       iii.      Maintenance of safe pedestrians and cyclists access across the
                                                 frontage of the site both during daily construction and after daily
                                                 construction has ceased.
                                       iv.       Sufficient parking arrangements for trucks, machineries and
                                                 construction workers without adversely impacting on traffic flow and/or
                                                 the availability of on-street parking in the local street.
                                b.          Maintenance and protection of water quality and existing drainage lines
                                            through the construction site through the implementation of appropriate
                                            erosion and sediment control measures.
                                c.          Works programme identifying key components of the works and their
                                            respective durations.
                                d.          The proposed dates for the commencement and the completion of the
                                            works.
                                e.          Effective procedures and measures to minimise adverse environmental
                                            impact on other properties and roads users including noise and dust
                                            emission.
                                f.          Establishment of a communication protocol with the adjoining owners and
                                            any other affected parties to advise of construction times, impacts on traffic
                                            and services and any other relevant issues.
                                g.          Identification of communication and complaint management procedures
                                            including:
                                            i.   Contact details for the on-site manager.



                                                                                                                  Page 8 of 21


Document Set ID: 20278602
Version: 1, Version Date: 22/02/2017                                                                     Print Date: 22 February 2017, 1:04 PM

Used in these records

About this file

File size
8.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

HRP18103.L02.002_Change application.pdf · 8.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.