ii. Dispute resolution procedures.
15. Any changes to the details associated with the supervising RPEQ or Principal
Contractor during construction, must be notified to council in writing within five
business days of the change occurring.
16. Any alteration to existing services or conflict between the development and an
existing or proposed service must be referred to the relevant service authority for
determination prior to commencement of works.
DURING CONSTRUCTION
General
17. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to
assets must be repaired immediately where it creates a hazard to the community.
In circumstances where the damage does not create a hazard to the community, it
must be repaired immediately on completion of the works associated with the
development.
18. All works must be supervised by a Registered Professional Engineer of
Queensland (RPEQ) who is independent of the Developer and Principal
Contractor, and they must certify that all works conform to the Operational Works
permit. Where municipal works are involved (eg pathway), such confirmation must
be submitted for the respective hold points prior to any site inspection by Council
Officers.
19. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans and conditions detailed in this Decision Notice.
b. All relevant Noosa Council Planning Scheme Policies, standard drawings,
standard specifications and guidelines, particularly PSP 5 – Engineering
Design Standards – Roads, Drainage and Earthworks.
c. The latest version of the Healthy Waterways document “Water Sensitive
Urban Design Technical Design Guidelines for South East Queensland” for
all water quality devices to be constructed on site.
Driveways
20. Driveway crossovers must be designed and constructed generally in accordance
with the approved plans and in accordance with IPWEA standard drawing RS- 051
and must have levels and grades that match the levels, width (2m) and the grades
of the existing concrete footpath without creating trip hazards.
21. The following must be complied with during the construction of the required
crossovers/driveways:
a. The driveway width must not exceed 6m at the front boundary line and 9m at
the kerb line.
b. The driveway surfacing must consist of either an approved hot mixed
asphaltic concrete or patterned/plain concrete and must have a slip resistant
surface.
c. The driveway must be constructed so as not to concentrate stormwater
runoff or ponding onto other properties and/or the road verge.
Page 9 of 21
Document Set ID: 20278602
Version: 1, Version Date: 22/02/2017 Print Date: 22 February 2017, 1:04 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
HRP18103.L02.002_Change application.pdfRelated documentApplication case desk ↗
About this file
- File size
- 8.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.