Council archive · source document
Delegated Report - Code - Planning MCU24 0153 & OPW24 0202 (As Published) · MCU24/0153
a. Dimensions and grades generally in accordance with Council standard drawings RS-
049 and RS-050.
b. safety measures, including warning signage, to improve driver awareness of
pedestrians and enhance pedestrian safety. Warning signage must be provided near
the exit ramp from the underground parking area to warn motorists of pedestrian
movement along the frontage street
Car Parking
24. A minimum of 12 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. 2 visitor parking spaces within the total, which are clearly marked for that purpose and
accessible at all times for visitor use;
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities;
25. Directional signage must be provided to direct visitors to the car parking spaces provided on
site.
Paving Treatment of Vehicle Movement Areas
26. Alternative materials, patterns, or threshold treatments must be used to articulate the
pavement treatment of vehicle movement areas.
Pedestrian and Bicycle Facilities
27. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. A 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to Elanda Street
Condition 27 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
28. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval and must include in particular:
a. Post-development peak flow rates must not exceed pre-development peak flow rates
up to a 1% AEP event, accounting for climate change and incorporating appropriate
detention measures
Condition 28 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Services
29. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
30. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Geotechnical Stability
31. All works must be carried out in accordance with the recommendations contained in the
Proposed Unit Development report prepared by Tectonic listed within this Decision Notice.
Page 22 of 28
Document Set ID: 23409043
Version: 7, Version Date: 18/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU24 0153 & OPW24 0202 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.