                                                                                                                                                                                 Town Planning Report
                                                                                                  28 Eenie Creek Road, Noosaville and parts of the road reserves of Hofmann Drive and Walter Hay Drive



A16 – Water Supply and Sewerage Reticulation Code
The below code response has been prepared by Cardno HRP and Cardno Engineering. In addition to the Town Planning Report, reference should be made to the
Engineering Report (Appendix E) in reading this code response.
Table 14-62 Water supply
 Specific Outcome                                         Probable Solution                                                          Response
 14.164 Design and construction (water)
 O1      Water supply infrastructure—                    S1.1     Water supply infrastructure is designed in accordance with         R1.1 Will Comply
         a) meets the needs of the users;                         PSP6 –Engineering Design Standards — Water and                     Detailed design of water supply infrastructure will be undertaken in
                                                                  Sewerage and As Constructed data submitted in accordance           accordance with the relevant Design Standards.
         b) is designed to be compatible with existing            with PSP6 –Engineering Design Standards — Water and
         infrastructure; and                                      Sewerage.                                                          Refer to Appendix E – Engineering Report.
         c) is designed using materials that are
         suitable for the use, durable, easy to
         maintain and cost effective, taking into
         account the whole of life cycle cost and
         Council’s maintenance inventory.
 O2      Water supply infrastructure is constructed—     S2.1     Water supply infrastructure is constructed in accordance with      R2.1 Will Comply
         a) in accordance with appropriate                        PSP6 –Engineering Design Standards — Water and                     Construction of water supply infrastructure will be undertaken in
         engineering standards; and                               Sewerage;                                                          accordance with the relevant Design Standards.
         b) to minimise adverse environmental                     AND                                                                Refer to Appendix E – Engineering Report.
         impacts.
                                                         S2.2     Erosion and sediment control measures are designed and             R2.2 Will Comply
                                                                  implemented in accordance with the Institution of Engineers        Refer to Appendix E – Engineering Report.
                                                                  Australia (Queensland Division) Soil Erosion and Sediment
                                                                  Control - Guidelines for Queensland Construction Sites.
 O3      Water supply infrastructure is proven to be              No solution provided.                                              R3 Alternative Solution (as no Probable Solution is provided)
         suitable for its use prior to Council                                                                                       An appropriate maintenance period can be conditioned as required.
         accepting the dedicated asset.
 O4      Water supply infrastructure is provided with             No solution provided.                                              R4 Alternative Solution (as no Probable Solution is provided)
         all supporting technical documentation.                                                                                     Technical documentation associated with any relevant infrastructure
                                                                                                                                     (e.g. valves and fittings) will be provided.
 O5      Where buildings or other structures are in      S5.1     The footing of any building or structure is located clear of the   R5 Alternative Solution
         proximity to State or Council’s water supply             zone of influence but no closer than 1.5m (measured                Design to be undertaken to ensure the requirements of O5 are met.
         infrastructure, provision is made to protect             horizontally) from infrastructure including sewers, water mains
         the infrastructure from physical damage and              and stormwater structures;                                         Refer to Appendix E – Engineering Report.
         to allow ongoing maintenance by Council.                 AND
                                                         S5.2     A registered easement in favour of Council is created over all
                                                                  underground infrastructure located in private property;
                                                                  AND




December 2014                                                                             Cardno HRP                                                                                           A105
Log in to download the original file

MCU14_0106 & OPW15_0001 Town Planning Report & Appendix A Code Compliance.pdf · 3.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.