MCU14/0106 & OPW15/0001 Town Planning Report & Appendix A Code Compliance
Original PDF page 187, section 1. The text section number identifies this passage in the reader.
Town Planning Report
28 Eenie Creek Road, Noosaville and parts of the road reserves of Hofmann Drive and Walter Hay Drive
Specific Outcome Probable Solution Response
S5.3 The width of the easement is the greater of 3m or the width of
the zone of influence;
AND
S5.4 The easement is centred over the centreline of the
infrastructure.
O6 Alignment of water supply infrastructure S6.1 Infrastructure is designed and constructed on the preferred R6 Alternative Solution
allows for easy access for the ongoing alignments in accordance with PSP6 Engineering Design Detailed design to be undertaken to ensure the requirements of O6
maintenance by Council. Standards – Water and Sewerage. are met.
Refer to Appendix E – Engineering Report.
O7 Any alterations or repairs to infrastructure S7.1 Any alterations or repair to infrastructure as a result of the R7.1 Can Comply
as a result of the development are made at development are completed at the developer’s expense. This matter can be conditioned if required.
no cost to Council.
Table 14-63 Sewerage Reticulation
Specific Outcome Probable Solution Response
14.165 Design and construction (sewer)
O8 Sewerage reticulation infrastructure— S8.1 Sewerage reticulation infrastructure is designed in R8.1 Will Comply
a) meets the needs of the users; accordance with PSP6 Engineering Design Standards – Detailed design of sewerage reticulation infrastructure will be
Water and Sewerage. undertaken in accordance with the relevant Design Standards.
b) is designed to be compatible with existing
infrastructure; and Refer to Appendix E – Engineering Report.
c) is designed using materials that are
suitable of the use, durable, easy to
maintain and cost effective, taking into
account the whole of life cycle cost and
Council’s maintenance inventory.
O9 Sewerage reticulation infrastructure is S9.1 Sewerage reticulation infrastructure is constructed in R9.1 Will Comply
constructed— accordance with PSP6 –Engineering Design Standards — Construction of sewerage reticulation infrastructure will be
a) in accordance with appropriate Water and Sewerage and As Constructed data submitted in undertaken in accordance with the relevant Design Standards.
engineering standards; and accordance with PSP6 –Engineering Design Standards —
Water and Sewerage; Refer to Appendix E – Engineering Report.
b) to minimise adverse environmental
impacts AND
S9.2 Erosion and sediment control measures are designed and R9.2 Will Comply
implemented in accordance with the Institution of Engineers Refer to Appendix E – Engineering Report.
Australia (Queensland Division) Soil Erosion and Sediment
Control - Guidelines for Queensland Construction Sites.
December 2014 Cardno HRP A106
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.