Parking Contributions
20. A Park contribution of $2,726 towards the acquisition of additional parkland or the
improvement of existing parkland and facilities in the locality shall be paid to the Council prior
to obtaining a Development Permit for Operational Works in accordance with Council’s
Planning Scheme Policy PSP24 Park Requirements. This amount will be subject to
variations in the Consumer Price Index, All Groups Brisbane from September 2004 until the
date of payment.
Frontage Works
21. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
Duke Street frontage of the site in accordance with Planning Scheme Policy PSP1
Landscaping Guidelines. Grass shall be couch, free of weeds.
22. All redundant vehicular crossings to the site shall be removed and replaced by kerb &
channel and landscaping such as trees and grasses in accordance with Council’s Standard
specifications prior to commencement of the use permitted by this permit.
Pathway Contributions
23. A pathway contribution of $247 towards external major pathways, in accordance with
Planning Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to
the Council prior to obtaining a Development Permit for Operational Works. This amount will
be subject to variations in the Consumer Price Index, All Groups Brisbane from September
2004 until the date of payment.
Stormwater Drainage
24. All stormwater drainage collected on the proposed buildings and landscaped areas shall be
collected on site and discharged to Council’s street drainage system in Duke Street. Plans
of the drainage design shall be prepared by a Registered Professional Civil Engineer and
submitted to Council prior to obtaining a Development Permit for Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s street drainage
system at any one location is 25 litres/second.
25. All stormwater drainage collected on the proposed driveways shall be disposed of on site.
To this end, a detailed design and maintenance plan for the on site disposal system shall be
submitted to the Council for approval prior to obtaining a Development Permit for Operational
Works.
A Development Permit for Building Works shall not be granted until a Development Permit
for Operational Works has been issued in regard to the drainage scheme.
26. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
27. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
28. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
29. Each water connection to the water reticulation system shall extend to the property boundary
and be metered. Where multiple units including leased buildings are served by a single
service, multiple water meters to each individual unit or leased building shall be installed. All
fees for the supply of water meters shall be paid to the Council.
Page 4 of 8
Document Set ID: 24833834
Version: 4, Version Date: 03/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - 132004 4552 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 168 KB (small file)
- File type
No other editions are linked here.