PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 08 AUGUST 2017
c. Any affected trees within the grassed verge must be replaced with similar species
in accordance with the landscaping conditions of this permit.
Car Parking
26. A minimum of 54 car parking spaces must be provided and marked on the site generally
in accordance with the approved plans. The works must be undertaken in accordance
with an Operational Works approval and must include in particular:
a. 3 disabled parking spaces within the total.
b. 3 visitor parking spaces within the total, which are clearly marked for that purpose
and accessible at all times for visitor use.
c. 18 bicycle parking spaces.
d. Dimensions, crossfalls, gradients and vehicle headroom in accordance with
Australian Standard AS2890: Parking Facilities.
27. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and maneuvering and kept in a tidy and safe condition at all times.
28. All car and bicycle parking areas must be line marked in accordance with approved
plans, no dividing walls be constructed unless a further application for amendment is
approved by Council.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval, and must include in particular:
a. Stormwater system that caters for all storms up and including 1 in 100 years
storm event.
b. No adverse impact on other properties and the road’s footpath and grassed verge
(eg by diverting flows and/or blocking flows and causing additional ponding).
c. Where applicable, extension of the site stormwater system to accommodate
stormwater from external site, including registration of drainage easements.
d. The use of gravity stormwater drainage only and not surcharge pits or pumps.
30. Stormwater runoff from the development must be disposed of without causing scour or
damage to the subject site or any adjoining property.
Electricity and Telecommunication Services
31. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
32. Certification must be submitted to Council from all relevant service providers which
certifies that the development has met the requirements of this Decision Notice and all
applicable legislation at the time of construction.
Easements
33. A 3 metre wide easement for “Public Thoroughfare” purposes must be registered
against the title of the property in favour of Council. The easement must be located
adjacent to the northern boundary of the subject property. The easement must:
a. Be clearly shown on all plans submitted for Operational Works.
b. Be registered prior to the commencement of the use.
Page 42 of 84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.