Decision Notice [As Published] · 132008.175
2008/175
43. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site.
44. To ensure that polluted run-off does not enter the water table, the adjoining waterways or
Council’s stormwater drainage system, stormwater run-off from the car parking areas and the
driveways shall have the first flush (the first 12mm of rainfall or hose-down) collected in a
grease/oil arrestor/gross pollutant trap provided on site prior to being permitted to discharge
into the larger drainage system.
All other clean stormwater, such as roof water, can be collected on site and discharged
through a single underground drain line directly into the existing drainage system, bypassing
the grease/oil arrestor/gross pollutant trap.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors/gross pollutant trap, which shall be submitted to the Council for approval prior to
obtaining a Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
45. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
46. The applicant must provide reticulated sewerage services to the proposed development in
accordance with The Noosa Plan.
47. A registered easement shall be created over the zone of influence of all sewers not currently
within an easement within the subject site. The easements shall generally be parallel to and
centred over the sewer main and be equivalent in width to twice the depth to invert level of the
sewer at the deepest point within the allotment (measured from the finished surface) and be
no less than 3.0 metres wide overall. A licensed surveyor shall accurately locate all sewer
mains and determine the necessary width of the easement which shall be shown on any plans
submitted for Operational Works or Building Works approval. The surveyor shall certify that
the sewer and the zone of influence is wholly contained within the easement to be created.
48. Buildings and structures shall maintain a minimum of 1.5 metres clearance from Council
sewerage infrastructure within the development site and shall be located clear of any existing
or proposed easement.
49. Proposed landscape planting within existing or proposed sewer easements shall be low
growing when mature and be suitable approved varieties in accordance with Council
guidelines for such plantings. Proposed tree plantings must be located a minimum of 1.5
metres from the Council rising main located in the adjacent lot.
50. A clear area of 1.0 metre must be maintained around the sewer inspection opening.
Town Water Supply
51. The applicant must provide reticulated water supply services to the proposed development in
accordance with The Noosa Plan.
52. The applicant must supply the development site with reticulated water via a single Council
installed primary water meter located outside the property boundary and in an easily
accessible location. For a community title or sub-lease scheme additional water meters must
be installed for each separate title. These meters must be supplied and installed in
accordance with Council’s requirements.
Page 7 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 579 KB (small file)
- File type
No other editions are linked here.