06/1168 - Change a Development Approval [As Published] · 132006.1168.02

of 199

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (20.7 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

necessary by the Superintendent, sand traps on the discharge line of any pump to prevent the deposit of
material in channels and stormwater drains.

Where water is diverted from the Site it shall be confined to existing drainage paths and away from
adjacent private property.

1.9 Setting-Out

Construction works set-out including road centreline pegging will be provided by the Contractor. The
Contractor is responsible for his own set-out using the plan coordinates and set-out details and the
Principal's survey information provided. The Contractor is responsible for maintaining all survey controls
during the course of the Contract. The cost of maintenance and reinstatement is the Contractor's
responsibility.

Survey information showing property and construction levels, dimensions and datum for levels is shown
on the drawings.

All work shall be set out by the Contractor in accordance with the information supplied.

The Contractor shail accept full responsibility for all setting-out and levelling and shall be responsible for
making good and bringing to required line and/or level any works which are wrongly built whether due to
error in transference of levels or dimension or to any other cause during setting-out.

The Contractor shall offset all essential engineering pegs during the works to enable the Superintendent
to carry out checks on line and level and to enable works to proceed in accordance with the program.

1.10 Public Utilities - Regulations, Notices and Fees

The Contractor shall carry out all work under this Contract in accordance with the provisions of this
Specification, and in addition shall comply with the latest requirements of the following and pay all
necessary fees:

» Local Council

» Australian Standard AS 3000 — (SAA Wiring Rules)

» Division of Occupational Safety and Weights and Measures
» The Building Act

» Inspection of Machinery Act

» Workplace Health and Safety Act

» Energex

» Any other Authority having jurisdiction over the work

Where overhead public utility lines and surface drainage works and/or underground pipes, conduits, or
cables exist in the vicinity of the works, the Contractor shall take care to protect such facilities from
damage and, in the case of any damage occurring to such facilities, the matter shall be immediately
reported to the department or company concerned and to the Superintendent. The cost of the necessary

41/22382/11840 Girraween Sports Precinct 9
Earthworks Package

Used in these records

About this file

File size
20.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_1168 - Change a Development Approval [As Published].pdf · 20.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.