NOOSA COUNCIL IDAS Development Application Decision Notice                                                          6


Erosion and Sediment Control

35.      Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
         control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
         waste, will be necessary.
         In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
         to the Council for approval prior to obtaining a Development Permit for Operational Works.
Vegetation Protection

36.      Vehicular pavements within the drip zone of any of the existing trees on site to be retained shall be
         designed as a pervious pavement (such as grass paving cells or similar), as this will allow water that falls
         on this surface to penetrate to the trees root system. The pavement shall be constructed so as not to
         damage the tree or their root system and in this regard temporary fencing shall be provided around the
         trees during construction to help protect them.
         Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
         pavement and the temporary fencing prior to obtaining a Development Permit for Operational Works.
Roadworks Contributions

37.      A roadworks contribution of $2,524 towards the Coastal Major Road Network in accordance with Planning
         Scheme Policy PSP42, shall be paid to the Council prior to obtaining a Development Permit for
         Operational Works. This amount will be subject to variations in the Price Index, All Groups Brisbane from
         March 2004 until the date of payment.
Pathway Contributions

38.      A pathway contribution of $246 towards external major pathways, in accordance with Planning Scheme
         Policy PSP41 Coastal Major Pathway Contributions, shall be paid to the Council prior to obtaining a
         Development Permit for Operational Works. This amount will be subject to variations in the Price Index,
         All Groups Brisbane from March 2004 until the date of payment.
General

39.      Any damage caused to any public utility during the course of construction shall be repaired to Council’s
         standards and at no cost to Council.

40.      Any alteration of any public utility or other facilities necessitated by the development of the land or
         associated construction works external to the site shall be at no cost to Council.

41.      The transportation of all materials to and from the site shall be undertaken in a manner such that no
         particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
         be covered to prevent materials including dust being windblown from the vehicle.

Building

42.      A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate lodged
         with Council at completion of the work confirming compliance with the maximum building height of 9
         metres above natural surface.

43.      All building works shall be in accordance with the Geotechnical reports prepared by Golder Associates
         dated July 2003 and Morrison Geotchnic dated 23 November 2006 subject to the following conditions:-

         43.1. An amended Geotechnical Report addressing the design amendments associated with this
               approval shall be submitted to Council for its information prior to the application for Operational
               Works;

         43.2. There is to be no uncontrolled discharge of water onto the slope;

         43.3. Stripping of vegetation for construction purposes should be minimised. If vegetation is destroyed it
               should be reinstated immediately after construction is completed;

         43.4. Additional load due to fill, construction equipment or stockpiled materials should not be located on
               the dune slope;




SEP o:\database\onestop\decision.doc

Used in these records

About this file

File size
50 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED COMPILED Decision Notice [As Published].pdf · 50 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.