PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 9 DECEMBER 2014
Stormwater Harvesting
19. Operating stormwater harvesting tanks must be provided for the development. The
tanks must be provided in accordance with an Operational Works approval and must
include in particular:
a. the details identified in section 5.0 and 6.0 of the of the Engineering report
dated 3 September 2013 by Barlow Shelly Consulting Engineers (with the
works expanded to reflect the extended development area).
LANDSCAPE & ECOLOGY
Landscaping Works
20. The development must be landscaped, in accordance an approval for Operational
Works. The particular works must generally accord with the planning scheme
Landscape Code and Planning Scheme Policy 3 Landscaping Plants and Guidelines
and include:
a. Landscaping to car park areas, including shade trees
b. Vegetated buffer to the Lake Macdonald Drive
c. Vegetated screening of any electrical transformers, bin storage areas and the
like from the road frontage
d. Details of any proposed clearing of vegetation and details of retention of any
existing trees on the site and road verge to accommodate the approved
development footprint. An Arborist Report is required to validate any proposed
clearing.
e. Removal of all weeds species listed in the following standards and legislation:
i. Declared plants under the Land Protection (Pest and Stock Route
Management) Act 2002 and sub-ordinate Regulation 2003
ii. undesirable species, as defined within Planning Scheme Policy 3
Landscaping Plants and Guidelines of the Noosa Plan.
21. All landscape works must be established and maintained in accordance with
horticultural best practice with construction techniques and irrigation that allow for
healthy, sustained and vigorous plant growth. All plant material must be allowed to
grow to full form and be refurbished when its life expectancy is reached.
Rehabilitation
22. The land area defined by the vegetated portion contained within the Riparian Buffer
Area of the Biodiversity Overlay of the Noosa Plan on the subject must be
rehabilitated in accordance with a rehabilitation plan prepared by a suitably qualified
person and an approval for Operational Works. Rehabilitation works must:
a. restore the habitat value of the land to meet the characteristics of the
appropriate regional ecosystem
b. return the land to its natural undisturbed state, where practicable. Where
impracticable, provide justification.
c. The treatment of undesirable species, as defined within Planning Scheme
Policy 3 Landscaping Plants and Guidelines of the Noosa Plan.
Page 96 of 134
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.