NOOSA COUNCIL IDAS Development Application Decision Notice                                                  5 of 16


28.   The turning bay shall be line-marked with chevrons and have the words “No Parking” painted on the
      pavement. A sign shall also be provided to indicate that the area is a “Turning Area Only” and that “No
      Parking is Permitted”.

29.   All carparking shall be kept, maintained and line-marked in a condition fit for use.
Frontage Works
30.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the David Low Way
      frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants & Guidelines.
      Grass shall be couch, free of weeds.

31.   A new 2.0m wide concrete path shall be constructed along the David Low Way frontage of the site in
      accordance with Council’s design standards and to an alignment that protects any significant vegetation
      or any underground services. The alignment of the new path where it joins the proposed access driveway
      be setback a minimum of 6.0m from the kerb and channel of David Low Way to provide sufficient room for
      a vehicle to stop on the driveway to give way to a pedestrian without impacting on the traffic on David Low
      Way.

32.   Any damage to the existing concrete footpath in the David Low Way road reserve that occurs due to the
      construction of the proposed development shall be reinstated to the satisfaction of Council’s Manager
      Land Development prior to the commencement of the use.

33.   All paths, driveways and parking areas shall be designed and constructed to ensure pedestrian safety
      using non-slip materials, to produce an evenly graded surface finish, and to be in accordance with the
      Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access & Mobility.

34.   All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
      paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
      prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
35.   Stormwater drainage for the development shall be generally as shown on the submitted drawing number
      010207-02 prepared by Saint Consulting Engineers, except as modified herein.

36.   Roof runoff from any building shall be directed to a rainwater storage system or tank (minimum storage
      5000 litres) that is installed to ensure water from the tank is used for external uses (such as watering
      gardens, irrigation, ornamental ponds, water features, outdoor cleaning, etc) and for use in flushing of
      toilets internal to the building. All rainwater tanks are to be designed and installed in accordance with the
      Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing
      application in conjunction with the building approval. The location and capacity of the tanks shall be
      clearly shown on the plans submitted for Building Works / Operational Works approval and any overflow
      shall be directed to the stormwater drainage system.

37.   All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
      collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
      drainage permitted to drain from the site shall be discharged to Council’s existing drainage structures
      located in the adjoining property at the rear of the site.
      The capacity of the Council drainage system shall be determined and the volume of stormwater
      discharged from the site restricted such that the capacity of Council’s existing drainage system is not
      exceeded.
      Plans of the drainage design shall be prepared by a Registered Professional Civil Engineer and submitted
      to Council prior to obtaining a Development Permit for Operational Works.
38.   The design of the stormwater drainage system for the carparking area and access driveway shall be
      sufficient to cater for a Q100 rain event or a suitable overland flow path shall be provided within the site.
      The stormwater drainage system shall be wholly contained within the subject site and shall not adversely
      affect the adjoining properties.

39.   As part of the subject site is proposed to be filled, appropriate stormwater drainage pipes shall be installed
      within the site to collect and discharge stormwater runoff from adjoining properties to prevent additional
      ponding/flooding on these properties.

40.   To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
      from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
      down) collected in a grease/oil arrestor/gross pollutant trap provided on site prior to being permitted to
      discharge into Council’s drainage system.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@8c06eccd\@[email protected]

Used in these records

About this file

File size
239 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2006.00000718.001 [As Published].pdf · 239 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.