A levelling layer under the floor slab is to comprise of granular material compacted in 150mm layers.
Either well graded sand or crusher dust can be used.

An approved polyethylene damp proof membrane of 0.2mm (min.) thickness is to be placed over. the
levelling layer. Laps are to be a minimum of 200mm and be taped. All service penetrations and punctures
are to be fully taped. The membrane is to be extended down the inside face of the perimeter footings.

Where rock is encountered within the slab area and encroaches within the slab depth it should be
excavated to a level which enables placement of a 100mm (min.) layer of granular material under the
slab.

Notes: - -- es

Alt building dimensions are to be obtained from the approved plans. The builder must ensure that the final
pier placement meets all the requirements of this report (both written specifications and cross-sections).

All excavations must be totally free of alt loose material and debris before pouring. They must be cleaned
out so that the concrete is poured onto undisturbed ground. Tamping and/or watering loose material is
not acceptable.

We strongly recommend footing excavations be inspected by a qualified person with appropriate
experience to confirm the founding material and level is as nominated herein.

Similarly all preparations should be inspected prior to the pouring of concrete by a qualified
person with appropriate experience to confirm that the workmanship and construction conforms
with the details and recommendations contained herein.

Tited Areas:

In areas where ceramic floor tiles or brittle coverings alike are required we recommend increasing the
size of the slab mesh by one grade. Use flexible adhesives when affixing tiles and delay the laying for as
long as possible (at least 3 months, preferably 6 months) after the slab is poured.

Reinforcement:

Reinforcement is to comply with the following:-

a) Concrete cover around the reinforcement must be 40mm to unprotected ground, 40mm to external
exposure, 30mm to the membrane in contact with the ground, and 20mm to the internal surface. The
slab fabric shall be placed towards the top of the slab within the zone defined by these limits. We
recommend 30mm top cover.

b) Slab fabric must be lapped by one full panel of fabric so that the two outermost transverse wires of one
sheet overlap two outermost transverse wires of the sheet being lapped. Slab fabric is to be supported on
bar chairs placed at 800mm ctrs.

c) Trench mesh must have all cross wires cut flush with the outer main wires. Trench mesh in slab and
edge beams must be overlapped by the width of the fabric at "T” & “L’ intersections. Trench mesh must
be spliced, where necessary, by a lap of 500mm,

d) Pre-Fabricated footing cages or reinforcing bars at “T” & “L” intersections are to have a Y12 corner
lapping bar top and bottom and lapped 500mm with adjacent bars.

e) The minimum tap length of reinforcing bar is to be 500mm or 25 bar diameters, whichever greater.

SCG CONSULTING ENGINEERS 4 SCG Ref: 17003(S)

Used in these records

About this file

File size
498 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2104 - Response to Information Request [As Published].pdf · 498 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.