2010/871
35.2. Stormwater runoff from the yard and driveway areas must be treated within the site and
discharged in a controlled manner as overland flow into the National Park. The
discharge must mimic existing drainage patterns and not cause scour or damage to the
National Park or the subject site.
Plans of the drainage design must be prepared by a Registered Professional Civil
Engineer and submitted to Council prior to obtaining a Development Permit for
Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel
street drainage system at any one location is 25 litres/second
36. To ensure that polluted run-off does not enter Council’s stormwater drainage system or the
adjoining National Park, stormwater run-off from the carparking areas and the driveways must
have the first flush (the first 12 mm of rainfall or hose-down) collected in a grease/oil
arrestor/gross pollutant trap provided on site prior to being permitted to discharge from the
site.
To this end, a detailed maintenance plan must be prepared for the proposed grease/oil
arrestors/gross pollutant trap, which must be submitted to the Council for approval prior to
obtaining a Development Permit for Operational Works.
The approved maintenance plan must be incorporated in the Community Management
Scheme for the development and a copy of this must be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works must not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
37. All site stormwater drainage must be by means of a gravity system.
Earthworks
38. Earthworks required on site must be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any natural
watercourses.
39. Earthworks carried out on site must not affect the structural integrity of any of the existing
fences and/or structures and/or lands that border the development site. Fences that are
affected must be replaced prior to the Building Certifier issuing the Certificate of Classification.
In this regard any fences to be replaced must be clearly shown on the plans submitted for
Operational Works approval.
Site Stability
40. A Geotechnical Engineer or similar qualified expert must assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures and/or land, and make recommendations on
the type of foundation system(s) best suited for the proposed development. The
recommendations of this report must be incorporated into the design and construction of the
proposed development.
Erosion and Sediment Control
41. Any person acting on this permit must prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary. In this regard plans detailing the methods of
controlling erosion and sediment are required to be submitted to the Council prior to obtaining
a Development Permit for Operational Works.
42. A suitably qualified Registered Professional Engineer must prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which must be
submitted in conjunction with an application for a Development Permit for Operational Works.
Page 7 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED SPA Decision Notice - 010.2010.00000871.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 859 KB (small file)
- File type
No other editions are linked here.