Landscape Specification
CONTENTS
Prior to the Practical Completion Inspection, the Contractor must provide the certificates below to the
Landscape Architect and Project Manager:
• Certification that all landscaping works have been completed in accordance with the approvals
• Soil Scientist certifications
• Pavements slip resistance certifications.
• Access certification that works meet all standard requirements.
• Wall, furniture and surface certification of anti-graffiti treatment.
• Maintenance manuals, parts and manufacture’s guarantees for all structures, furniture, pavement, seals,
fixtures or other used products.
• Playground completion package that includes:
o Certification.
o Installation manuals.
o Softfall surface attenuation testing results in accordance with AS4422, Playground surfacing
o Specifications, requirements and test method.
End of Establishment Maintenance Inspection
Four months prior to the agreed end of establishment period the Contractor, the Landscape Architect, the
Superintendent and the Project Manager shall carry out a joint Inspection to ensure all landscape works are
maintained as agreed.
Items identified requiring attention, during the inspection are to be addressed immediately or as agreed.
Quality Control Inspection
Two weeks prior to the agreed end of establishment period the Contractor and the Landscape Architect shall
carry out an Inspection to ensure all landscape works are ready for the hand-over.
Items identified requiring attention, during the inspection are to be addressed immediately.
Handover
At the end of establishment period the Contractor, the Landscape Architect, the Superintendent and the
Project Manager shall carry out a joint Inspection to ensure all landscape works are maintained and cleaned
to the client’s expectation.
Prior to the Handover the Contractor must provide the certificates below to the Project Manager:
• Arborist certification that all trees and palms in public land have been inspected and rectification works
for public safety and longevity of the tree/s have been completed.
• Prove of completion of all maintenance works which were required within the 52 weeks period by the
manufacturers recommendation.
URBIS
URB-SPC-LAN-P0025138 - IFC.DOCX PAGE 72
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.