erosion. d) A combination of the principles in these documents; adverse environmental impacts occur.
AND For details regarding the proposed erosion and sediment control
measures to be implemented during the construction phase please refer
S9.2 Erosion and sediment control measures are to the Engineering Plans, included within Appendix D of this report.
designed and implemented in accordance with the
Institution of Engineers Australia (Queensland Division)
Soil Erosion and Sediment Control - Guidelines for
Queensland Construction Sites.
Environmental Protection S10.1 Roads and stormwater drainage follow the edge Complies.
O10 Roads and stormwater drainage of existing disturbed areas or alternatively, these
infrastructure are located and aligned so as works are co-located within a combined utility corridor; All stormwater runoff from the subject site will drain to either the
to— AND 10,000L retention tank or the bio-retention basin. Both the retention
a) minimise disturbance to native vegetation S10.2 Roads avoid native vegetation and provide for tank and bio-retention basin will be connected to Council’s stormwater
and/or other habitat areas; fauna underpasses and associated fencing where infrastructure. The proposed stormwater management design will
b) protect and maintain wildlife corridor appropriate; ensure stormwater runoff from the subject site does not have any
movements and the safety of native fauna; AND impacts external to the subject site.
c) minimise changes to the hydrological S10.3 Road infrastructure within or adjacent to native
regime, including drainage patterns, run-off habitat incorporates fences which allow for protected
and water quality; wildlife movement and controls unrestricted access of
d) avoid crossing watercourses, drainage domestic cats and dogs;
lines and wetlands, but where such crossings AND
are unavoidable, disturbed areas are S10.4 Native vegetation is protected from clearing or
reinstated and revegetated on completion of construction activities by—
works; and a) clearly marking vegetation to be retained with
e) minimise bulk earthworks. flagging tap;
b) installing protective fencing around the dripline of
vegetation; and
c) ensuring stock piling, storage and vehicle parking
occur outside the areas of vegetation to be retained;
AND
S10.5 Low impact construction techniques are used
around areas of vegetation to be retained to minimise
interference with the vegetation.
O11 Roads and stormwater drainage No solution provided Not applicable.
infrastructure is proven to be suitable for its
use prior to Council accepting the dedicated The only stormwater infrastructure proposed is private stormwater
asset. infrastructure to be connected to Council’s stormwater main. No
stormwater infrastructure to be dedicated to Council is proposed.
O12 Alignment of stormwater drainage S12.1 The location, design and construction of Not applicable.
infrastructure is to allow for easy access for stormwater drainage structures is in accordance with
the ongoing maintenance by Council. Sections 4 and 5 of PSP5, Engineering Design The only stormwater infrastructure proposed is private stormwater
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Collated Planning Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 8.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.