b. Front fences are no more than 1.2 metres high or 1.8 metres if at least 80% transparent.
c. Be setback an average of 1 metre with dense screening landscaping between boundary
and fence.
Waste Management
16. A waste storage area must be provided in accordance with Planning Scheme Policy 9, Waste
Management and the Noosa Plan’s Waste Management Code, including an external
imperviously paved area correctly sized for all refuse and recycling containers and suitably
screened from public places and neighbouring properties.
Community Management Statement
17. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
Landscaping Works
18. The development site must be landscaped. The works must be undertaken in accordance
with the Operational Works approval and the Noosa Plan for that specific area and must
include in particular:
a. the works shown on the Approved Plans.
b. all landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
19. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
20. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the landscaping works conditions of
this Decision Notice.
*(Refer to Advisory Note)
External Works
21. Southern Cross Parade must be upgraded for the length of its frontage to the subject site.
The works must be undertaken in accordance with the conditions held within this Decision
Notice, be generally in accordance with RECOR’s Stormwater Layout Plan (040, Rev. B)
dated 23 February 2023 and must include in particular:
c. construction of kerb and channelling and underground stormwater drainage to the
development side only;
d. removal of the existing property access and reinstatement of the kerb, footpath (1.5-
metre-wide) and verge area to match the balance of the site frontage, including the
provision of topsoil and turf where the existing verge is grassed; and
e. construction of a 1.5-metre-wide pedestrian footpath across the full length of the
frontage and in accordance with the conditions of this Decision Notice.
Site Access and Driveways
22. A sealed access driveway must be provided from Southern Cross Parade to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
the conditions held within this Decision Notice and be generally in accordance with RECOR’s
Driveway Layout Plan (010, Rev. B) dated 23 February 2023.
Page 14 of 25
Document Set ID: 22435587
Version: 8, Version Date: 15/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU22 0197 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.