                      preferred to have the footpath continue at a constant grade to minimise the potential for
                      pedestrians to trip or fall.
               Pathway Contributions
               17.    A pathway contribution of $252 towards external major pathways, in accordance with
                      Planning Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to
                      the Council prior to obtaining a Development Permit for Operational Works. This amount
                      will be subject to variations in the Consumer Price Index, All Groups Brisbane from June
                      2005 until the date of payment.
               Stormwater Drainage
               18.    All stormwater drainage shall be collected on site and discharged so there is no net
                      increase in stormwater runoff from the site and generally in accordance with the
                      Pavement and Stormwater Plan and Details – Drawing No. S3064/05/R1.
               19.    Roof runoff from the new dwelling shall be directed to a rainwater storage system or tank
                      (minimum storage 3000 litres) that is plumbed to service the toilets in the new dwelling
                      and landscaping areas. The design of the rainwater storage system shall be to the
                      satisfaction of the Manager Plumbing Services.
               20.    The overflow runoff and all other stormwater shall be collected on site and discharged
                      through the proposed infiltration pit.
                      To this end, a detailed maintenance plan shall be prepared for the proposed infiltration pit,
                      which shall be submitted to the Council for approval prior to obtaining a Development
                      Permit for Operational Works.
                      The approved maintenance plan shall be incorporated in the ongoing maintenance for the
                      development.
                      A Development Permit for Building Works shall not be granted until a Development
                      Permit for Operational Works has been issued in regard to the drainage scheme.
               21.    All site stormwater drainage shall be by means of a gravity system.
                      Mechanical pump out systems shall not be used to dispose of surface stormwater
                      runoff not being reused in toilets and landscaping.
                      Overflow from the reuse system shall be by gravity system.
               Sewer Mains
               22.    The dwelling shall be connected to Council’s existing sewerage reticulation systems and
                      be constructed in accordance with Council’s standards and requirements at no cost to
                      Council.
               Town Water Supply
               23.    The dwelling shall be connected to Council’s existing town water supply and be
                      constructed in accordance with Council’s standards and requirements at no cost to
                      Council.
               Earthworks
               24.    Earthworks carried out on site shall not affect the structural integrity of any of the existing
                      fences or structures that border the development site. Fences that are affected shall be
                      replaced prior to plan endorsement. In this regard any fences to be replaced shall be
                      clearly shown on the plans submitted for Operational Works approval.
               Site Stability
               25.    A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
                      determine the soil classification, establish whether any measures are required to protect
                      the stability of adjoining buildings and/or structures, and make recommendations on the
                      type of foundation system(s) best suited for the proposed development. This information
                      shall be submitted to the Council prior to obtaining a Development Permit for Operational
                                                                                                           Page 4 of 7


Document Set ID: 23097952
Version: 4, Version Date: 11/07/2024

Used in these records

About this file

File size
158 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 132005 307 01.pdf · 158 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.