Stormwater Management Plan




7              MUSIC Modelling

7.1            Summary
MUSIC Version 5.1.16 was used in the analysis. The MUSIC Modelling Guidelines for South East
Queensland (Healthy Waterways, 2010) were used as the main reference to set up the models.
The rainfall data was taken from Cooroy Composite (40059) for the 10 year period from the 1/1/1973 to
31/12/1982. A 6 minute time step was adopted.
The MUSIC model layouts for each precinct are shown in Appendix E.

7.2            Catchment Areas
The sub-catchment areas are shown in Figure 2.
The rainfall runoff parameters and pollutant export parameters were taken from Tables 3.7 and 3.8 of the
MUSIC Modelling Guidelines.
For the existing case a rural-residential node was used, with a 0 percent impervious value. For the
developed case an urban-residential nodes were used, except for a small area of commercial development
in Area C. The residential areas were assumed to be 60 percent impervious, townhouses, apartments and
retirement living areas were assumed to be 70 percent impervious.
The breakdown of road, roof and ground area was based on the concept masterplan layout. For precincts
where the layout has not been specified typical surface type splits from Table 3.3 of the manual were used.
                                                                          2
The roof area of premium residential lots was assumed to be 250 m , and the roof area for standard
                                         2
residential lots was assumed to be 215 m in accordance with Table 3.3. All of the available roof area will be
connected to rainwater tanks so as to maximise stormwater harvesting on site.
The new access roads have been included in the MUSIC modelling. The upgrade of existing Council roads
will be undertaken on behalf of Council or by Council, at a cost to the development. These roads will be
provided with best practice stormwater quality treatment. These road upgrades have not been included in
the MUSIC modelling.
The breakdown of each sub-catchment is shown in Table 7-1.
Table 7-1      MUSIC Sub-catchments

  Catchment       Total Area             Roof                              Road                     Ground
    Name             (ha)        Area       Percent Im-          Area         Percent Im-   Area        Percent Im-
                                 (ha)        pervious            (ha)          pervious     (ha)         pervious
                                                (%)                               (%)                       (%)
      1_B_1          1.200       0.425            100           0.161             60        0.614            32
      1_B_2          1.948       0.525            100           0.566             60        0.857            36
      1_B_3          0.555       0.225            100                                       0.330            33
      1_B_4          1.280       0.325            100           0.490             60        0.465            32
      1_B_5          0.895       0.325            100           0.112             60        0.458            32
      1_B_6          0.139                        100           0.139             60
      1_C_1          1.264       0.442            100           0.379             70        0.442            30
      1_D_1          3.911       1.369            100           1.173             70        1.369            30
      1_D_2          0.833                                      0.833             60
      1_D_3          0.278                                      0.278             60
      1_E_1          3.174       1.111            100           0.952             70        1.111            30



Northbrook Corporation Pty Ltd                        Version 4                                      16 September 2013
SMP_v4.docx                                     Commercial in Confidence                                      Page 18

Used in these records

About this file

File size
10.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 16- Amended Stormwater Management Plan MCU12_0208.pdf · 10.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.