Attachment 16- Amended Stormwater Management Plan MCU12/0208

of 66

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Noosa on Weyba
Stormwater Management Plan



drain the roof areas to the road, rather than directly to underground drainage. The resultant load removal for
the combined site was 83% for TSS, 60% for TP and 48% for TN.
While the water quality objectives can be met if the bio-retention areas are increased it is still recommended
that rainwater tanks be adopted on site. The proposed development aims to promote the use of ecologically
sensitive design and the use of rainwater tanks plays an important role in this regard. As this will be a Body
Corporate development there will be more control available on the development conditions for each lot. The
use of rainwater tanks will significantly reduce the water demand of the site and allow the remaining
treatment devices to be better utilised treating ground and road runoff, rather than relatively clean roof runoff.

8.4            Frequent Flow Objective
The developed area of the site is 56.36 hectares, and is on average 62.5 percent impervious. The first 15
mm of runoff from impervious surfaces is therefore 5.28 ML/day. Based on the 10 years of rainfall data used
in the MUSIC modelling, the average annual runoff from the first 15mm of runoff from impervious surfaces is
equivalent to 317.2 ML/year. The total average annual runoff was 607.8 ML/year.
The MUSIC model was used to determine how much of the runoff was being treated by the bio-retention
basins and swales. The rainwater tanks were removed from the modelling, so that there were no other
outflows. The amount of runoff being treated by the bio-retention basins and swales alone was 364.7
ML/year. This is greater than the amount of runoff generated from the first 15mm of rainfall from impervious
surfaces, and therefore the frequent flow objectives are met.
The proposed rainwater tanks have a total volume of 6.375 ML. The daily usage is on average 0.282
ML/day, or 103.1 ML/year. The proposed tanks supply around 84.5 ML/year of this non-potable demand.
Therefore the total flow being treated or removed will be greater than that modelled without the rainwater
tanks in place.

8.5            Waterway Stability
The waterway stability objective is met as the peak flows from the site have been reduced to existing case
levels for all ARI events up to and including the 100 year ARI event (refer Flood Study, Cardno, September
2013). This is due to the attenuation being provided by the proposed road crossings and detention basins.
The attenuation provided by the rainwater tanks and bio-retention basins was not included in this analysis.
Therefore the attenuation, particularly for minor events, will likely be greater than reported.
Bio-retention basins and rainwater tanks provide some attenuation of minor peak flows, typically up to the 2
year ARI event. The stormwater outlets throughout the site should have adequate scour protection installed
to prevent downstream erosion.




Northbrook Corporation Pty Ltd                     Version 4                                     16 September 2013
SMP_v4.docx                                  Commercial in Confidence                                     Page 26

Used in these records

About this file

File size
10.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 16- Amended Stormwater Management Plan MCU12_0208.pdf · 10.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.