Attachment 3 - Construction Management Plan · OPW25/0206

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                       Construction matters and measures to be implemented
                                             Chemical Storage
Storage of            Control measures for chemical storage to be implemented include:
chemicals such as             Storing all chemicals in sealed containers in weatherproof lockable
herbicides, fuels             storage
and surfactants               Storing copies of SDS’ for all chemicals
                              Removing chemicals at the end of each day and safely storing them off
                              site
                              Providing spill kits onsite
                                                     Dust
Airborne Dust         Dust control measures may include:
                              Earth moving management
                              Covering loads
                              Limiting cleared area
                              Site traffic control
                              Soil compaction
                              Watering sprays
                              Vegetative stabilisation
                                                     Noise
Noise associated      Construction work that makes audible noise must be carried out under the
with construction     following conditions:
including vehicles,            Between the hours of 7am and 5pm, Monday to Friday
voices, workers       Noise control measures to be implemented may include:
and radios etc.                Maintaining all machinery and equipment in good working order
                               Locating noisy site equipment, where possible, being structures that act
                               as barriers or at a distance from noise sensitive areas
                               Orienting equipment so that noise emissions are directed away from
                               noise sensitive areas
                               RACV to give prior notification to the community and adjoining property
                               holders when noisy operations are to be conducted
                               RACV to implement complaint management process and procedures
Noise associated      Regulated devices include such items as lawnmowers, generators, power tools
with regulated        and compressors:
devises                        Are not to be operated before 7am and after 5pm, Monday to Friday or
                               on any other day at any time
                      Noise control measures to be implemented may include:
                               Maintaining all regulated devices in good working order
                               Orienting regulated devices so that noise emissions are directed away
                               from noise sensitive areas
                Protection of Council assets (streets, footpaths, laneways and reserves)
Protection of          Control measures to protect council assets such as streets, footpaths, laneways
Council assets         and reserves include:
(streets, footpaths,           Planning site usage to restrict vehicles from crossing gutters and
laneways and                   footpaths
reserves)                      Not overloading vehicles and ensuring gutters and footpaths are not
                               subject to potentially damaging loads
                               Protecting pavements and gutters with barriers




                                      P.O. Box 320, Eudlo           E. [email protected]
                                      Queensland, 4554,             P. 0408 011 584 | ABN 18 766 198 454
                                      Australia                     www.biodiverse-environmental.com.au


                                FLORA | FAUNA | REHABILITATION | FIRE | WATER

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 3 - Construction Management Plan.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.