Pensasr Project Construction Management Plan

Attached to the e-mail Operation Works Application - OPW19/0266 - 215 David Low Way, Peregian Beach (EMAIL 3/3) - Fauna Management, Landscaping, Bushfire Management, Environmental Management, Waste & Preliminary Construction Management Plan.

of 11

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                    Project Management Plan

2.         Project Scope and Objectives
2.1        In Scope
This defines the project boundaries to facilitate effective management of deliverables on time and to
agreed/approved cost.
The scope of works for 215 David Low Way, Peregian Beach, includes all design related aspects from
initial conception to issuing of for construction plans, production of as constructed documentation and
final submission to Council (including plan sealing and cadastral survey set out and registering of
properties). In summary the design aspects includes;
      •   Full Civil Construction design (bulk earthworks stormwater, sewerage, water reticulation,
          roadway, etc.)
      •   Electrical Design including conduit alignment, pit locations, cabling details, location of pad mount
          transformers, property connections any additional electrical fixtures;


In relation to the construction works, the scope of works defined within the For Construction plans will
generally entail the following items;
      •   Stripping of Topsoil;
      •   Bulk Earthworks (approximately of imported 12,000m3 earthworks);
      •   All drainage installation including inter-alotment drainage to the legal point of discharge;
      •   Construction of gravity sewerage reticulation to the existing sewerage network;
      •   All electrical reticulation installation to service including pits, pipe, cabling, jointing and any other
          items required within the electrical design;
      •   Construction of water reticulation network
      •   Preparation of subgrade and placement of gravel within the newely defined roadway, potential
          construction of concrete roadways to be reviewed
      •   All quality assurance testing of the aforementioned items to the minimum requirements of the
          relevant local authority (i.e. Noosa Shire Council, Unitywater, Energex, etc.) will form part of the
          scope works.


2.2        Out of Scope
The following items are considered to be out of scope for Pensar/ this document:
      •   Building works and any allotment construction works unless noted within the Civil Design
      •   Concrete roadways and subgrade preparation are considered out of scope at this stage
      •   Any other items discussed to be excluded during the tender review process
2.3        Project Objectives
Include here a statement of what the project is expected to achieve including potential benefits based
upon the current state of knowledge and understanding, e.g.:
      •   Construction of a specific stage of a high standard subdivision.
      •   Meet client expectations and time targets.
      •   Close co-operation with other parties operating in the vicinity of the site.
      •   Develop close relationships with all stakeholders (e.g. neighbouring property owners).
2.4        Project Specific Constraints
The project objectives for 215 David Low Way located at Peregian Beach include the following;


 Project Management Plan (GRP-PLN-001-PROJECT NUMBER)                                          January 2019, Rev: 5
 215 David Low Way, Peregian Beach/ G20-010                                                          Page 6 of 11
Log in to download the original file

Pensasr Project Construction Management Plan.pdf · 373 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.