Noosa Shire Council
Charges Resolution (No.8) 2024
Part 4 Offset and refund for Council trunk
infrastructure
11. Infrastructure offset
11.1 Purpose
Section 11 states the Council’s policy for calculating the establishment cost for an
infrastructure offset for provision of trunk infrastructure. This section is to be also read in
conjunction with the “Minister’s Guidelines and Rules”.
11.2 Application of section
Section 11 applies where for a development, the Council has for a trunk infrastructure
network:
(a) requires trunk infrastructure to be provided under a necessary
infrastructure condition of a development approval, that services or is
planned to service premises other than the subject premises; and;
(b) a levied infrastructure charge applies to the development.
11.3 Establishment cost for an infrastructure offset
The establishment cost for determining offsets for provision of trunk infrastructure
required in a necessary infrastructure condition shall be the establishment cost
identified in the LGIP or Netserv Plan and indexed to the reference date of the
issued infrastructure charges notice.
11.4 Recalculation of establishment cost for an infrastructure offset
(1) Where a notice is given by an applicant under s. 137 of the Planning Act
requesting a recalculation of the establishment cost for the trunk infrastructure
that is works, the recalculated amount shall be the pre-market estimate of the
work as follows: The pre-market estimate of work for the trunk infrastructure
contribution is the estimate expressed in dollars of the design and construction of
the work:
(a) including the following:
(i) the cost of planning and designing the work;
(ii) the cost of survey and site investigation for the work;
(iii) a cost under a construction contract for the work;
(iv) a portable long service leave payment for a construction
contract;
(v) an insurance premium for the work;
(vi) a Council inspection fee for the commencement and end of the
maintenance period for the work;
Council Resolution effective 15 August 2024 Page 48 of 90
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.