Noosa Shire Council
Charges Resolution (No.8) 2024
(vii) the cost of an approval for the work;
(b) excluding the following:
(i) a cost of carrying out temporary infrastructure;
(ii) a cost of carrying out other infrastructure which is not part of the
trunk infrastructure contribution;
(iii) a cost of the decommissioning, removal and rehabilitation of
infrastructure identified in paragraphs (i) and (ii);
(iv) a part of the trunk infrastructure contribution provided by the
Council or a person other than the person seeking the
infrastructure offset;
(v) a cost to the extent that GST is payable and an input tax credit
can be claimed for the work.
(c) The applicant:
(i) must undertake a tender process in accordance with the
Council’s Procurement Policy for any work contribution which is
eligible for an Infrastructure Offset under this document;
(ii) must give the Council a Notice which states the claimant’s
calculation of the pre-market estimate, which will include, as
applicable;
A. a copy of the tender advertisement;
B. a copy of each tender received;
C. the claimant’s preferred tenderer;
D. the claimant’s reason for the preferred tenderer;
E. a copy of the proposed Work Contract issued by the
claimant’s preferred tenderer;
F. detailed plans and specifications showing the extent of
the Work Contribution eligible for an Infrastructure
Offset;
G. the claimant’s calculation of the cost providing a Works
Contribution to which an Infrastructure Offset applies;
H. the total of the claimant’s calculation of the Pre-Market
Estimate.
(iii) If the Council agrees with the applicant’s Pre-Market Estimate, it
becomes the establishment cost of the infrastructure.
(d) If the Council does not agree with the applicant’s Pre-Market Estimate,
the Council will provide its own alternative Pre-Market Estimate to the
applicant. If the applicant agrees with the Council’s alternative Pre-
Market Estimate, it becomes the establishment cost of the infrastructure.
Council Resolution effective 15 August 2024 Page 49 of 90
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.