Extension to Currency Period Report REC14/0005.04 {As Published}
EXTENSION TO CURRENCY PERIOD – DELEGATED REPORT
approval was initially issued on 2 November 2023 and was subject to representations which
were not resolved until 21 May 2024.
Enacting the ROL has been on hold pending the outcome of this MCU application. Now that
the MCU approval is in place, this extension is sought in order to provide time for the ROL to
be enacted.
This extension to the currency period is sought to allow time to obtain necessary operational
works approvals and undertake the works necessary to enact the ROL. The 5-year extension
is also sought to align the ROL approval with the MCU approval recently obtained over the
site, which remains current until 26 October 2029, one month after the requested currency
date for this ROL approval.
2. BACKGROUND
• A development approval to Reconfigure 1 lot into 2 lots was issued on 4 July 2014.
• An extension to the current period was granted on 27 September 2018 which extended the
currency period to 25 September 2020.
• A minor change to the approval and an extension to the current period was granted on 3
November 2020 which extended the currency period to 25 March 2023. This currency period
included the first ministerial currency period extension (‘Covid extension’) of six (6) months
within the extension.
• The second ministerial currency period extension (‘Covid extension’) of six (6) months took the
currency period out to 25 September 2023.
• The third ministerial currency period extension (‘Covid extension’) of 12 months took the
currency period out to 25 September 2024.
• A Development Permit for a Material Change of Use – Hardware and trade supplies
(MCU22/0051) was approved by Council on 26 October 2023 for development over the
currently vacant portion of the lot (proposed Lot 103). A subsequent Negotiated Decision Notice
was issued on 21 May 2024.
• Upon receipt of this extension to the current period application (REC14/0005.04), Council
provided advice to the applicant to update conditions of the existing approval to align with the
recent MCU22/0051 approval. A minor change to the approval application (REC14/0005.05)
was lodged on 10 September 2024 seeking amendments to conditions to align with the
requirements of the MCU approval. The application is being assessed concurrently with the
subject application (REC14/0005.04).
3. ASSESSMENT
The applicant has requested an extension to the currency period to the development approval
under section 86 of the Planning Act 2016.
The previous extension to currency period was approved 3 November 2020 following the
commencement of the current Noosa Plan 2020, with the assessment report stating:
Since the last extension to currency in 2018 Council has adopted a new Planning Scheme,
the Noosa Plan 2020. Although the Council’s planning scheme has changed, there has been
no changes to the new Planning Scheme that would affect the assessment of the approval if
it were remade today and therefore proposal remains consistent with the new Planning
Scheme.
The application was referred to Councils water quality Officer as water quality treatment
requirements have changed since the original approval. The existing conditions are sufficient
with the development able to meet the current water quality requirements.
It is also noted that the proposed lot sizes comply with minimum lot size requirements of 1000m2
under both the 2006 and 2020 planning schemes.
Page 2 of 3
Document Set ID: 23093969
Version: 5, Version Date: 04/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Extension to Currency Period Report REC14/0005.04 {As Published}Related documentApplication case desk ↗
About this file
- File size
- 537 KB (small file)
- File type
No other editions are linked here.