8. APP G. Engineering RFI Response
Attached to the e-mail MCU14/0102 - Response to Information Request - Email 2 of 2..
Original PDF page 18, section 1. The text section number identifies this passage in the reader.
A comparison of the parameters listed in Table 4.1 demonstrates that the proposed
development will not increase the rate of stormwater runoff discharged from the site as the
proposed development does not change the existing impervious area and stormwater runoff
volumes. Therefore, no onsite detention is required to mitigate peak discharge flow rates.
Stormwater runoff from the proposed development site can be discharged directly to the lawful
point of discharge, which for Catchment 1 is Lionel Donovan Drive.
CATCHMENT 2 DISCHARGE
Catchment 2 is an internal catchment on Lot 4 on SP159610. In its existing state, the catchment
area is used for retail and automative purposes.
Table 4.2, below, lists the catchment characteristics for the site.
Table 4.2 – Peak discharge flow rates comparision
PARAMETERS EXISTING DEVELOPED
Approx. Developed Area 0.26 0.24
Fraction Impervious 1 0.9
Coefficient of Runoff (C10) 0.9 0.88
Coefficient of Runoff (C50) 1.0 1.0
Time of Concentration 5 minutes 5 minutes
A comparison of the parameters listed in Table 4.2, above, demonstrates that the proposed
development will not increase the rate of stormwater runoff discharged from the site as the
proposed development does not change the existing impervious area and stormwater runoff
volumes. Therefore, no onsite detention is required to mitigate peak discharge flow rates.
Stormwater runoff from the proposed development site can be discharged directly to the lawful
point of discharge, which for Catchment 2 is Eumundi Noosa Road.
CATCHMENT 3 DISCHARGE
Catchment 3 is an internal catchment that covers all of Lot 31SP170751. In its existing state, the
site is undeveloped.
CATCHMENT PARAMETERS
A summary of the catchment parameters is presented in Table 4.3.
Table 4.3: Summary of Catchment Areas
PARAMETERS EXISTING DEVELOPED
Approx. Developed Area 0.42 0.47
Fraction Impervious 0.1 0.90
Coefficient of Runoff (C10) 0.72 0.89
Coefficient of Runoff (C50) 0.83 1.00
Time of Concentration 17.7 minutes 5 minutes
Stormwater Management Plans
Page 6 Hyder Consulting Pty Ltd-ABN 76 104 485 289
f:\aa007595\f-reports\f0002-aar-aa007595 sbswmp report\f0002-aa007595-aar-04.-smp.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.