Skip to the record
Trusted by locals. Built for Noosa.

Original source · versioned page text

8. APP G. Engineering RFI Response

Attached to the e-mail MCU14/0102 - Response to Information Request - Email 2 of 2..

of 68

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 27, section 1. The text section number identifies this passage in the reader.

                is required to be installed to collect vehicle dispensing spillage, blown in rain and tanker delivery
                spillages.

                It is recommended to engage a suitably qualified hydraulic consultant to design the Fuel
                Dispensing Area (FDA), Uncovered Forecourt Area (UFA) and the tanker unloading area
                hydraulic management systems.

                CONSTRUCTION PHASE WATER QUALITY
                An Erosion Hazard Assessment has been carried out for the proposed development – refer to
                Appendix I for a copy of the completed Noosa Council form. As a result of this assessment, it
                was determined that the site is a ‘low’ risk. During the construction phase of the development,
                an Erosion and Sediment Control Program (ESCP) will need to be implemented to minimise
                water quality impacts. A detailed Erosion and Sediment Control Program will be employed
                throughout the site.

                Details of the ESCP measures shall be provided on the operational engineering drawings for
                the site earthworks and civil engineering works. The contractor shall be responsible for the
                provision of the construction phase water quality objectives which shall be enforced by the
                preparation and implemention of an Erosion and Sediment Control Program.

                The ESCP shall be provided to all people involved with the construction, including sub-
                contractors, private certifiers and regulators. These guidelines will be formed in accordance with
                the Healthy Waterways Fact Sheet ‘Erosion and Sediment Control Management Plans’ and the
                ‘Best Practice Erosion and Sediment Control Guidelines.’




139 Eumundi Noosa Road & 30 Lionel Donovan Drive, Noosaville Service Station and Retail Site—Stormwater
Management Plans
Hyder Consulting Pty Ltd-ABN 76 104 485 289                                                                       15
f:\aa007595\f-reports\f0002-aar-aa007595 sbswmp report\f0002-aa007595-aar-04.-smp.docx
Log in to download the original file

8. APP G. Engineering RFI Response.pdf · 5.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.