ECM_16693990_v1_APPROVED Change to Existing Approval 152005 220 01
Attached to the e-mail 132005.220.04 Request a Change Existing Approval.
152005.220.01
Stormwater Management Plan May 2007, Revision 1, dated 14/09/07. This
requirement shall be included on the Plan of Development.
82. Stormwater quality will be monitored for a period of three years after endorsement of
the Plan of Survey. The results shall be analysed and submitted to Council in digital
form with an executive summary describing the corrective measures required (if any).
Those measures will then be implemented to ensure compliance with the water quality
objectives.
Services Generally
83. Conduits and kerb markers shall be installed for all necessary service crossings of
roads to Council's satisfaction. An ‘As Constructed’ plan showing the locations of the
conduits shall be submitted to Council prior to acceptance of the works ‘On
Maintenance’.
84. All sag points in trenches excavated for the installation of underground infrastructure
shall be drained to a drainage pit.
85. Subsoil drains shall be used to ensure pits, manholes or other structures do not dam
trenches.
86. Any alteration of a public utility or other facility necessitated by the development of the
land or associated construction works either internal or external to the site shall be at
no cost to Council.
Service Easements
87. Registered easements shall be created over all water mains and sewerage mains
within private property. The easements shall generally be parallel to and centred over
the main and be equivalent in width to twice the depth to invert level of the main at the
deepest point within the allotment (measured from the finished surface) and be no
less than 3.0m wide.
88. An easement shall be created over any stormwater drainage within private property
and dedicated to Council at no cost. The width of the easement shall be sufficient to
provide a minimum of 1.5m either side of the designed drainage structure and shall be
at least 4m wide.
89. A minimum of a 1.5m wide easement shall be created over all private drainage
lines/inter-allotment drainage (if any). The terms of the easement shall include the
responsibilities on the beneficiaries of the easement to maintain the drain so as to be
operational at all times.
90. A registered easement shall be created over all overland flow paths in favour of
Council, unless the overland flow path is on Council road reserve or is within a Council
Park Reserve. The easement shall extend the full length and width of the Q100 major
storm event surface flow path and be created at no cost to Council.
91. A licensed surveyor shall accurately locate all existing services and determine the
necessary easement widths in accordance with the abovementioned conditions, which
shall be clearly shown on all plans submitted for Operational Works approval. All new
services required for the development, and their expected easements, shall also be
clearly indicated on the plans submitted for Operational Works approval.
92. Prior to Council endorsement of the Plan of Survey for the Lot Reconfiguration, a
licensed surveyor shall have accurately determined the necessary service easements
in accordance with the abovementioned conditions for all existing services and all new
services provided based on their “as constructed” positions.
Environmental
93. All Class 1, Class 2 and Class 3 pest plants declared under the Land Protection (Pest
and Stock Route Management) Act 2002 are to be controlled on the site prior to
FM1512s/1-07/04/2010 Page 11 of 19