ECM_16693990_v1_APPROVED Change to Existing Approval 152005 220 01
Attached to the e-mail 132005.220.04 Request a Change Existing Approval.
152005.220.01
Council endorsement of the plan of survey. In this context ‘controlled’ shall mean, for
Class 1 and 2 pests, completely eradicated. For Class 3 pests it shall mean removal
of the plants where they threaten environmentally significant areas of the site such as
riparian zones and areas of natural vegetation.
Where Class 3 plants are removed as a result of this condition and there is not
sufficient natural regeneration of native species, the areas shall be replanted with
endemic native species so that a sustainable natural ecosystem is restored.
Council’s Conservation Management Supervisor will not inspect the site until 30 days
after the weed treatment and replanting is complete.
94. A plan outlining all vegetation to be removed (such as the existing camphor laurel
trees) and all vegetation to be retained on site shall be submitted to Council for
approval prior to Council issuing a Development Permit for Operational Works.
95. All vegetation to be retained shall be protected from interference resulting from
clearing or construction activities by:
95.1. Clearly marking vegetation to be retained with flagging tape;
95.2. Installing protective fencing around the drip line of the vegetation;
95.3. Stockpiling, storage and vehicle parking occurs in already cleared areas and
does not cause interference with vegetation; and
95.4. Low impact construction techniques are used around vegetation to minimise
interference with the vegetation.
96. A minimum of 5 days prior to commencement of any clearing works Council’s
Environment & Landscape delegate shall be contacted to arrange a pre-start
inspection of the marked area to be cleared and retained vegetation protection
measures in accordance with the above conditions. No clearing is to commence until
written approval has been granted by Council.
97. A Revegetation and Rehabilitation Management Plan (RRMP) for all Park Reserves
and Road Reserves shall be prepared and submitted to Council for comment and
approval prior to applying for a Development Permit for Operational Works.
The RRMP shall aim to revegetate these areas with suitable native species to
resemble the pre-cleared ecosystem by removing all noxious and environmental
weeds from the site, then planting suitable native species and then by carrying out
continual maintenance over a 3 year period (the maintenance period) to enable the
revegetation and rehabilitation works to be self-maintaining. The RRMP is to contain:
97.1. A 3 year maintenance period from the date restoration works are completed by
the contractor,
97.2. Performance criteria/objectives and a schedule of works to be achieved during
the operational works stage and the works required over the 3 year
maintenance period,
97.3. Details of site preparation (this may include thinning, grass removal, weed
removal and control, etc),
97.4. Measures to protect existing native plants on site during works,
97.5. Proposed planting, including local species type, size, location, and number of
plants,
97.6. Details on the establishment of the missing floristic and structural elements,
natural recruitment, habitat creation and fauna linkages, planting and mulching
procedures, fertilizing procedures, watering procedures, erosion and sediment
control, on-going maintenance, environmental safeguards.
FM1512s/1-07/04/2010 Page 12 of 19