App D - Development Approval
Site Access and Driveways
10. A sealed access driveway must be provided from formation of the existing internal sealed
driveway to the proposed secondary dwelling location. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. a driveway generally in accordance with drawings numbered 23064-C002 Rev A,
23064-C301 Rev A, 23064-C302 Rev A, 23064-C303 Rev A and 23064-C304 Rev A
prepared by Sunshine Coast Civil Engineering dated 27 October 2023, and
b. the recommendations contained in the Slope Stability Geotechnical Report reference
No W7363 sl A prepared by Sunrise Design Qld Pty Ltd dated 26 September 2023.
Stormwater Drainage
11. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Easements
12. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
13. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
14. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
15. All earthworks and associated batters must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments and in
accordance with the recommendations contained in the Slope Stability Geotechnical Report
reference No W7363 sl A prepared by Sunrise Design Qld Pty Ltd dated 26 September 2023
16. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the recommendations contained in
the Slope Stability Geotechnical Report reference No W7363 sl A prepared by Sunrise
Design Qld Pty Ltd dated 26 September 2023 and that the development has a minimum
factor of safety against landslip of 1.5 in the long term.
*(Refer to advisory Note)
Damage to Services and Assets
17. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Page 3 of 6
Document Set ID: 22713984
Version: 3, Version Date: 04/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (App D - Development Approval.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.