2014-09-16 Planning & Organisation Committee Agenda
The original of this document is very large (16.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 16 September 2014
Development Permit for Operational Works (Vehicle Crossover, Landscaping,
Drainage Works and Carparking)
OPERATIONAL WORKS
Approved Plans
1. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following
table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
1193-SK01 Driveway Layout, prepared by Contour 1 July 2014
1193-SK03 Stormwater Management Plan, prepared by 7 July 2014
Contour
4416SM PB Stormwater Plan, prepared by I Want That 17 July 2014
Design
1193-SK04 A Live Sewer Works Table 2 Sept 2014
CD-001 A Cover Sheet Notes and Schedules, prepared 3 July 2014
by DFS Group
CD-002 A External Works and Planting Plan, prepared 3 July 2014
by DFS Group
CD-003 A Landscape Details, prepared by DFS Group 3 July 2014
2. Development authorised by this approval must be undertaken generally in accordance
with the Approved Plans listed within this Decision Notice.
Prior to Commencement of Works
3. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6244.
The pre-start meeting must include the relevant parties for the following aspects of the
works:
a. Civil engineering works;
b. Erosion and sediment control works
4. A Construction Management Plan must be submitted to Council prior to the pre-start
meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction
ii. Maintenance of safe pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the
development
iv. Adequate parking arrangements for construction workers
b. Maintenance and protection of water quality and existing drainage lines through
the construction site through the implementation of appropriate erosion and
sediment control measures
c. Works programme identifying key components of the works and their respective
durations
Page 74 of 145
See the original
The page text is free to read. Viewing or downloading an original file needs an account.