Page 3

Traffic— Measures to minimise impact as follows:-
1. Demolition phase of Construction:-

a)

b)

c)

Provisions have been made to mobilise and demobilise each
item of plant and equipment during out of normal working
hours between Monday and Saturday with a pilot escort service
through Noosa where required, to minimise the impact on the
local community. The use of the plant and equipment is subject
to Sunshine Coast Regional Councils’ approval.

Demolition of Seahaven 3 to be loaded out utilising 10t Tippers.
Strategies to be in place in conjunction with our Traffic
Management Plan to minimize the impact on the local
community. Minimising the number of trucks to move the
material from site. Staggering all vehicles so that there is no
undue congestion on Hastings Street. No parking and/or
standing of plant on Hastings Street. All plant must be of sound
condition and well maintained.

Demolition of Seahaven 1 & 2 and all other associated areas to
be loaded out utilising Truck and Trailer, 30t capacity. This
change in transport is to minimise expense, time and to reduce
the impact of traffic flow on Hastings Street. This is first subject
to Sunshine Coast Regional Councils’ approval and once space
has been established for plant to maneuver on site.

2. Construction Phase of the Project:- ;
a) Construction vehicle parking impacts will be minimized by car

b)

pooling, onsite parking when available and parking outside the
immediate Hastings Street precinct.

A designated drop-off and construction parking zone will be
established on site and including the use of street parking bays.
This zone will enable delivery vehicles and plant such as cranes
and concrete pumps to safely park and enter/exit the project.
Traffic controllers will be used in this area where required to
warn members of the public on the footpath of the moving
equipment and to safely direct the vehicles and plant. Efforts
will also be taken by Hutchinson Builders to reschedule any
plant and material movements outside busy public access
periods.

Develop a footpath and road management plan to control heavy
and light construction

ee,

 

 

 

Used in these records

About this file

File size
24.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_1787 - Response to Information Request [As Published].pdf · 24.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.