MCU14/0106 Appendix E - Engineering Report

of 175

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (24.1 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 116, section 1. The text section number identifies this passage in the reader.

Noosa Civic
Construction Environmental Management Plan



Table 4-2          General nuisance noise level limits

     Sensitive              Time of Day       Acoustic quality objectives (measured at the          Environmental
     Receptor                                                   receptor)                               Value
                                              LAeq,adj,1hr      LA10,adj,1hr        LA1,adj,1hr
     Dwelling               Daytime and           50                55                 65             Health and
    (outdoors)                evening                                                                 wellbeing
     Dwelling               Daytime and           35                40                 45             Health and
     (indoors)                evening                                                                 wellbeing

Management Measures

 Tasks                                    Actions / Monitoring                                                                           Timing           Responsibility
 Advise residents, land owners            Erect signage at the site in a place viewable by local residents, land owners and patrons      Two weeks        Contractor
 and patrons of the current               displaying generic details of the works program with the proposed timeframe, or provide        prior       to
 facilities who may potentially be        this information in the form of a mail out/letter box drop to potentially affected residents   commencem
 affected by construction activities      and landowners.                                                                                ent         of
 of the works program.                    Ensure communications provide a point of contact for complaints, including a contact           construction,
 Notify community members of              telephone number which is manned during working hours, and a 24-hour emergency                 and ongoing
 construction site working hours,         contact number.                                                                                thereafter
 and clearly state these on               Ensure that the impacts in the interaction between construction works and the ongoing
 signage at the site.                     use of surrounding land uses is minimised as far as practicable by:
                                               engaging in ongoing weekly communications with surrounding land users so as to
                                                communicate constructions plans for the week and potential disruption to
                                                surrounding land users; and
                                               implementing the necessary management measures and controls to minimise any
                                                impacts (i.e. erecting signage, fencing, protection nets, etc).

 Minimise activities resulting in the     Operate and maintain all vehicles and equipment in accordance with the manufacturer’s          Ongoing          Contractor
 introduction of excessive dust and       specifications.
 fumes to the local atmosphere as         Do not undertake burning of waste materials at the site.
 far as practicable.
                                          Ensure all loads entering and exiting the site are securely covered to avoid dust
                                          generation.
                                          Cease any dust-generating activities during windy conditions.
                                          Deploy water trucks when dust is visible beyond site boundaries for longer than 15
                                          minutes.


Noosa Civic                                                                       Version 1                                                                November 2014
Appendix B - Construction EMP.docx                                                                                                                              Page 23
Log in to download the original file

MCU14_0106 Appendix E - Engineering Report.pdf · 24.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.