MCU14/0106 Appendix E - Engineering Report
The original of this document is very large (24.1 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Original PDF page 118, section 1. The text section number identifies this passage in the reader.
Noosa Civic
Construction Environmental Management Plan
Tasks Actions / Monitoring Timing Responsibility
arrangements.
Maintain construction site in an Manage construction activities and materials to ensure the site is maintained in a neat Ongoing Contractor
orderly and neat fashion. and tidy manner.
Store and respread topsoil as soon as practicable to minimise visual disturbance
associated with excavation activities.
Minimise visual impact of site Ensure stockpiles, storage areas and site parking are restricted to designated areas Ongoing Contractor
compounds. only.
Clean-up site as soon as Remove all vehicles, construction equipment, materials and refuse from the site as soon On Contractor
practicable following completion as practicable on completion of works. completion of
of works. works
Provide appropriate fencing, The construction worksite at each construction stage shall be securely fenced off with Ongoing as Contractor
signage and other control appropriate signage to prevent unauthorised entry to worksite. necessary
measures to prevent
unauthorised entry to the
construction sites.
Record keeping. Maintain records of any monitoring results including details of corrective actions and Ongoing Contractor
repairs/maintenance undertaken.
Maintain records of any enquiries/complaints received in relation to construction works
including complainant details, nature of complaint and corrective actions undertaken.
Ensure all records and reports are made available to relevant administering authorities
upon request.
Corrective actions Should there be non-compliance with the stated performance indicators the following Ongoing Contractor
corrective actions are to be implemented:
identification of the cause of the non-compliance;
implementation of appropriate mitigation measures as determined by the
Principal in consultation with the Contractor and relevant experts (where
required); and
relevant validation monitoring to confirm that the nominated corrective
actions have been effective.
The Contractor shall implement the corrective action(s) as required within the agreed
timeframe noted on the CAR.
Noosa Civic Version 1 November 2014
Appendix B - Construction EMP.docx Page 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.