Noosa Civic
Erosion Sediment Control Plan
3 Erosion and Sediment Management
3.1 Methodology
The Contractor’s proposed erosion and sediment control methodology is to be implemented in four distinct
phases in accordance with construction activities being undertaken.
Phase 1 – Prior to Construction commencement
Phase 2 – Bulk Earthworks
Phase 3 – Civil Construction
Phase 4 – Post Construction
Sediment basin/s is/are to be established, as require, prior to works commencing in the basin’s catchment
area.
The site is to be filled in a cellular fashion, in that the external fill batters are to be filled and stabilised first
prior to the infilling of the fill areas. The entire earthworks area will be managed by the Contractor in a logical
and reasonable sequence.
3.2 Soil and Stockpile Management
All reasonable and practicable measures must be taken to obtain the maximum benefit from existing topsoil.
Viable topsoil is to be stockpiled in long low flat mounds to facilitate the survival of seed and micro-
organisms vital for the topsoil.
Stockpiles of erodible material that has the potential to cause environmental harm, if displaced, must be:
Appropriately protected from wind, rain, concentrated surface flow and excessive up-slope
stormwater surface flows.
Located at least 2m from any hazardous area, retained vegetation, or concentrated drainage line.
Located up-slope of an appropriate sediment control system.
Provided with an appropriate protective cover (synthetic, mulch or vegetative) if the materials are
likely to be stockpiled for more than 28 days.
A suitable flow diversion system must be established immediately up-slope of a stockpile of erodible material
that has the potential to cause environmental harm if displaced, if the up-slope catchment area draining to
the stockpile exceeds 1500m 2.
3.3 ESC Installation sequence
Prior to land disturbance
Item Removed
Mark out initial limits of disturbance / mark out No Go
Zones
Entry / Exit installed Upon site completion
Install sediment weir After construction of Sediment Basin
Clear sediment basin and stockpile areas
Install sediment fence to stockpile areas After stockpile removal
Install Sediment Basin and stabilised outlet Upon site completion
Install clear water diversion and repair as required
QIC Noosa Civic Pty Ltd Version 1 November 2014
Appendix C - ESCP.docx Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.