Noosa Civic
Construction Environmental Management Plan
2 Objectives
This CEMP provides clear performance criteria for the construction phase of the development that are to be
met in order to minimise adverse impacts to the receiving environment. In particular, this CEMP provides
mechanisms whereby the environmental performance associated with the construction works can be
measured, and provides procedures for the implementation of agreed corrective actions, if required.
To satisfy the above objectives, this CEMP addresses the following key components:
Rationale: identification of the element to be managed and the potential for environmental impact of
activities associated with each element;
Objectives: identification of the environmental objectives and targets to be achieved in line with the
rationale and in compliance with applicable legislation;
Tasks/Actions: monitoring and management measures to be implemented in order to achieve the
stated objectives and targets to ensure impact mitigation;
Performance Indicators: measurable indicators and standards set to assess the efficiency of
management measures and determine compliance with the associated operational plans;
Monitoring: monitoring requirements to measure compliance with the performance indicators and
frequency of monitoring;
Reporting and Review: the requirements for reporting of monitoring results and review of management
measures where required; and
Corrective Actions: measures to be undertaken should monitoring indicate non-compliance with
performance indicators.
The CEMP is a flexible living document which should be updated to reflect any changes in the project and be
updated with any self-monitoring, feedback and reviews conducted.
This CEMP shall be reviewed if the construction design undergoes substantial changes prior to
commencement of the works.
The Contractor undertaking the works shall assume responsibility for the implementation of this CEMP.
Noosa Civic Version 1 November 2014
Appendix B - Construction EMP.docx Page 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.