BUNNINGS WAREHOUSE, NOOSAVILLE
SURFACE WATER MANAGEMENT PLAN (4:^ Car-dna
F1 For the purposes of the modelling, sensible device parameters based on outline quantity
calculations were input to the model, as described in the table below. If the layout of the
site changes in future these can be amended to suit, providing that the overall effectiveness
is maintained. The bio-retention device is modelled as a single large device, for example,
where in fact several smaller devices of equal total capacity would be employed in the car
park landscaping divides around the site.
Table 11 Bioretention Device Parameters
Parameter Value
Surface Area (m) 860
Extended Detention Depth (m) 0.1
Filter Area (m) 860
Filter Depth (m) 0.5
Mean Particle Diameter (mm) 0.36
Saturated Hydraulic Conductivity (mm/hr) 180
Overflow Weir Width (m) 2
Rainwater tanks provide some reduction in nitrogen loads, thought to be via biofilm activity
within the tank. The reduction in overall runoff through storage and reuse will also minimise
loads at the site outlet. To enable a conservative quality assessment, only a nominal
rainwater tank size was used, having a volume of 18kL and a surface area of 8m2. A
realistic re-use demand of 1250kL per year was applied. This size is conservative given
the likely rainwater tank size to be adopted (refer Section 5).
4.8 Modelling Results
The results of the MUSIC modelling, shown as total annual loads, are presented in the
table overleaf. It can be seen from the tables that the treatment train would reduce all of
the total loads released from the developed site to such an extent that the target reductions
are achieved for all pollutants.
Table 12 Total Annual Loads
Total Suspended Total Total Total Gross
Situation
Solids Phosphorus Nitrogen Pollutants
Existing Site
t (Rural Res)
Development
Potential
3,000 kg/yr
6,880 kg/yr
6.27 kg/yr
18.5 kg/yr
34.1 kg/yr
106 kg/yr
196 kg/yr
683 kg/yr
Development with
1240 kg/yr 5.20 kg/yr 54.8 kg/yr 0 kg/yr
treatment train
Realised Reduction 82 % 72 % 48 % 100 %
Target Reduction 80 % 60 % 45 % 90 %
Note that the proposed development, owing to its water sensitive urban design
measures, produces lower annual pollutant loads than the existing rural residential
case, for most of the modelled pollutants.
I
' Bunnings Warehouse Version 1 15 December 2006
J \3501 541WP15WMP doc Commercial in Confidence Page 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
OPW11/0023 Development Application part 2 of 2 Planning Report and Plans 178 Eumundi Noosa Road NoosavilleRelated documentApplication case desk ↗
About this file
- File size
- 70.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.