7am to 7pm: Maximum background + 5dB(A);
7pm to 10pm: Maximum background + 3dB(A);
10pm to 7am: No audible noise.
29. Submission of written certification from a suitably qualified person confirming that the noise
levels from all mechanical equipment comply when measured at either the residential
boundary or outside the most exposed part of an affected building, whichever is the closest
to the equipment.
The assessment and certification is required immediately after installation of the equipment
and prior to any occupation of the building, and in a format approved by Council. All
equipment should be operating at the same time to test the overall noise level created.
DEMOLITION
Performance Bond
30. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
be submitted to Council prior to the issue of a Development Permit for Building Works for
demolition, to secure the demolition conditions of this approval. The cash bond or trading
bank guarantee will be returned on performance of the demolition conditions of this approval
less any costs incurred by Council in respect of enforcing performance of these demolition
conditions. Council reserves the right to call upon the bond or guaranteed sum to effect
compliance with conditions.
Works
31. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste management
32. A Waste Management Plan (demolition) must be submitted in accordance with Planning
Scheme Policy PSP9 - Waste Management and approved by Council’s Waste Coordinator
prior to issue of a development permit for Building Works for demolition, removal or
relocation.
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
effective reuse and recycling of such materials. Segregated wastes attract significantly
reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
mixed waste.
Waste storage areas must provide for adequate separation of all reusable, recyclable and
waste materials. These must be located so that they are convenient and safe to use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table in accordance with Planning Scheme Policy PSP9
- Waste Management - SC6.10.4
Note * If a demolition contractor is undertaking works, then the Waste Management table is
to be completed by the demolition contractor.
Page 5 of 12
Document Set ID: 21313305
Version: 5, Version Date: 08/12/2020 Print Date: 8 December 2020, 2:48 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.