Attachment 9- Amended Bushfire Assessment Report MCU12/0208
Very large file (11.7 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Noosa on Weyba
Bushfire Assessment Report
It is also noted that reduced BAL requirements for residential and commercial buildings adjacent to
hazardous vegetation may be permitted if a more detailed analysis of BAL requirements is carried out in
accordance with the Detailed Method for Determining the Bushfire Attack Levels (Method 2) of AS3959-2009
Construction of buildings in bushfire prone areas. Such an assessment is outside of the scope of this report.
4.2 Water Supplies
The SPP 1/03 Guideline states that, for all development involving new or existing buildings with a gross floor
2
area greater than 50m , each lot has:
a) a reliable reticulated water supply that has sufficient flow and pressure characteristics for fire
fighting purposes at all times (minimum pressure and flow is 10 litres a second at 200 kPa); or
b) an on-site water storage of not less than 5,000 litres (e.g. accessible dam or tank with fire
brigade tank fittings, swimming pool).
The Noosa on Weyba project would be serviced by a reticulated water supply that would be available for fire
fighting/suppression purposes. To ensure that access to this reticulated water supply is readily available for
fire suppression and property protection purposes in the event of a bushfire, a series of hydrants should be
established around the perimeter of proposed residential precincts.
The establishment of a reticulated water supply servicing the Noosa on Weyba project would also be of
benefit to adjacent residents who are dependent on rain fed storage facilities (e.g. tanks and dams) for a
supply of water for fire management purposes. Given that high risk bushfire periods typically coincide with
periods of low rainfall the reliability of rain fed storage facilities can be limited, unless diligently managed by
the dependent residents.
The Noosa on Weyba project also incorporates an Integrated Water Cycle Management system capturing
100% of all roof water which would provide a backup water source for fire fighting should the mains supply
be interrupted.
4.3 Lot Layout and Siting
It is a requirement of the SPP 1/03 Guideline that lots be designed so that their size and shape allow for the
following.
1. Efficient emergency access to buildings for fire-fighting appliances (e.g. by avoiding long narrow lots
with long access drives to buildings).
2. Setbacks and building siting such that buildings can be situated in locations of lowest hazard within
the lot and appropriate setbacks from hazardous areas can be established and maintained.
In respect of the above, it is noted that internally the Noosa on Weyba Concept Master Plan generally:
> avoids the creation of long narrow allotments and each of the proposed building areas has direct road
frontage to facilitate emergency access and egress; and
> makes appropriate provision for buildings setbacks (see Section 4.1) and the establishment of necessary
firebreaks and fire maintenance trails (see Section 4.4).
The general lot layout and roadway arrangements illustrated in the arrangements Noosa on Weyba Concept
Master Plan are similar, in terms of their exposure to hazardous vegetation, to the arrangements that occur
with the existing urban development to the north of Eenie Creek and the Weyba Downs development to the
south.
The proposed Rural Residential area contained within Precinct Four is the only proposed building site where
a “long driveway” is proposed through areas of potentially hazardous vegetation. It is noted that SPP 1/03
does not define what constitutes a “long driveway” and in that respect the following guidance contained in
the NSW Rural Fire Service guide Planning for Bush Fire Protection (2006) is relevant:
“Travel distances of 200 metres or more are particularly problematic in that it is difficult to traverse
with dense smoke and reduced vision as well as the increased chance of being isolated by the
advancing fire. Trees close to the access track become obstacles in the hazy environment.
Northbrook Corporation Pty Ltd Version 2 11 October 2013
Bushfire Assessment Report v2.docx Commercial in Confidence Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 9- Amended Bushfire Assessment Report MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.