MCU10/2065

 

 

 

 

 

39. Submission of written certification from a suitably qualified person confirming that the
noise levels from all mechanical equipment comply when measured at either the
residential boundary or outside the most exposed part of an.affected building,
whichever is the closest to the equipment.

40. The assessment and certification is required immediately after installation of the

- equipment and prior to any occupation of the building, and in a format approved by.
_ Council. All equipment should be operating at the same time to test the overall noise
level created.

41. Advice: It is highly recommended that the person you engage to certify the installation
is involved at the plan development stage so they can-recommend where this
equipment is best located. They can also advise about noise enclosures and can make
other suggestions to avoid noise problems. it is a lot more costly to try and deal with

noise problems after everything is built.

42. Noise from residential building works shall comply with the following -

42.1. Limited to between 7:00am to 6:30pm Monday to Saturday.
42.2. All reasonable measures are taken to minimise noise emissions.
42.3. Not permitted on Sunday or public holidays.

UNITYWATER ‘

43. The fire-fighting demand on Unitywater’s water supply system from the development
must not exceed 165 litres per second

44, Separate 25mm PE water services must be installed to a common lot boundary with
independent. meters: installed outside the boundary of the lot in accordance with
Unitywater Standard Drawing SCW 361

45. Water meters must be located on alternative boundaries to electrical pillars

46. Buildings and other structures must maintain a minimum clearance of 1.5 metres from
Unitywater sewer mains, and 1.0 metre from sewer manhole chambers and inspection
openings

47, The storm water retention system must be located a minimum of 1. 5 metres from
Unitywater sewerage infrastructure

48. Stormwater pipes greater than 225mm diameter must maintain a minimum clearance
of 1.0 metre from Unitywater sewerage infrastructure

49. The level of the existing sewer manholes must be adjusted to suit the proposed

: finished surface levels. Work must be undertaken by Unitywater at the applicants cost
..§0.--Tree--plantings.must.maintain..a.minimum.horizontal..clearance..of 1.0 metre. from
Unitywater water mains and 1.5 metres from Unitywater sewerage mains. Landscaping
plants within these clearances must be low growing when mature and suitable
approved varieties

51. Construction works undertaken in the vicinity of Unitywater water supply or sewerage

: infrastructure must not adversely affect: thé integrity of the infrastructure. All costs
associated with repair, replacement or alteration of infrastructure must be met. by the -
applicant

L&
Not Applicable
[:6. "APPR NS/DOCUMENTS .

 

 

The approved plans and / or documents for this development approval are listed in the.
following tables:

PD-DA-FM384/1-13/04/2010 SO, : Page 7 of 13

Used in these records

About this file

File size
2.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

01072015144724.pdf · 2.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.