OPERATIONAL PLAN 2024-25 Q3 QUARTERLY REPORTING (Referred from Services and Organisation Committee Meeting dated 10 June 2025 - Item 8.1) · Attachment 1 - Q3 Operational Plan Update
Plans and drawings: the text below has words only, no drawings.
Initiatives on Target
OP Ref Initiative Service/Mgr Responsible Status Reason for Status
4.5.1 Complete the Place Pilot Program in Pomona and Strategy and Sustainability On Track Final Pomona Place Plan endorsed by Council March 2025.
share learnings to improve the future of the Manager Evaluation report under preparation.
program and inform future planning for Pomona.
4.6.1 Undertake preliminary planning for the Brisbane Sport and Active Lifestyle On Track Continuing to evaluate latest developments and actions on
Olympics and Paralympics 2032. Manager games planning through CoMSEQ. Internal discussions with
relevant impacted portfolios has started. We have paused
commencement of internal working group until more is known
on overall Brisbane 2032 strategic direction.
4.6.2 Develop and maintain relationships with key Sport and Active Lifestyle On Track Officers and Councillors attending various COM SEQ
Brisbane 2032 stakeholders. Manager committees and meetings to ensure involvement when
required/appropriate.
4.7.1 Develop the Emissions Offset strategy/plan and Strategy and Sustainability On Track Roadmap to Net Zero Emissions project is currently in
road map towards Zero emissions for council Manager procurement phase with the series of Councillor workshops
services. having already started. Minor delays experienced due to staff
resource limitations and procurement hurdles. Estimate
completion by end of calendar year.
4.8.1 Advance the Sunshine Coast and Noosa Regional Strategy and Sustainability On Track Completing Stage 6 and 7 of the project including the economic
Climate Action Roadmap by delivering the Manager analysis for Noosaville Depot and sharing lessons learned more
Regional Cascading Risks and Critical broadly. On track for final completion by EOFY with embedding
Infrastructure Failure Project with Sunshine Coast of project findings as the next step.
Regional Council.
4.8.3 Complete the implementation of the Disaster Community Services On Track Final reconstruction projects near completion. Human social
Recovery Plan for the 2022 Floods & Rain Event. Director Recovery Plan completed.
4.8.4 Continue the implementation of the Coastal Strategy and Sustainability On Track Phase 2 of the Coastal Wetland Restoration Project with
Hazards Adaptation Plan (CHAP), including Manager University of Queensland and KKPAC is underway. An initial site
planning for Living Foreshores Noosa, Coastal assessment on Cooloothin Cr Nature Refuge has been
Wetland Restoration Project. undertaken and grant funding is being sought through
QCoast2100 Round 3. Living Foreshores Noosa continues to
advance with Hilton Esplanade due to restart this quarter.