Bill of Quantities · OPW24/0125
ITEM NO. DESCRIPTION UNIT QUANTITY RATE TOTAL
SECTION 4 : STORMWATER DRAINAGE
4.1 Supply, lay and joint BlackMAX PE pipes, including trench excavation, bedding and
surround sand, backfill, compaction and disposal of spoil as specified:-
(a) 600mm dia m 23 360.70 $ 8,156.51
(b) 750mm dia m 36 432.90 $ 15,584.40
4.2 Construct Grated Field Inlet pits grate cover and surround to existing pit as per design
drawings complete
(a) 600x600 No 1 6,112.00 $ 6,112.00
(c) 900x900 No 1 7,640.00 $ 7,640.00
4.3 Supply and install Humeceptor STC-3 GPT complete in accordance with design
drawings and suppliers specifications No 1 25,000.00 $ 25,000.00
4.4 Modifications to existing inlet pits complete in accordance with design drawings No 2 3,820.00 $ 7,640.00
4.5 Modifications to exisitng access chambers complete in accordance with design
drawings No 1 4,584.00 $ 4,584.00
4.6 Modifications to existing outlet structures in accordance with design drawings No 1 5,500.80 $ 5,500.80
4.7 Supply and install precast concrete headwall to stormwater outlet complete
(a) 600mm dia No 1 1,875.80 $ 1,875.80
TOTAL SECTION 4
$ 58,352.60
STORMWATER DRAINAGE
QUANTITIES ILLUSTRATED HEREIN ARE ESTIMATES FOR TENDERERS INFORMATION ONLY. TENDERERS ARE REMINDED THAT THIS IS A LUMP SUM CONTRACT AND ALL QUANTITIES MUST BE CONFIRMED BY THE
TENDERER IN THEIR TENDER SUBMISSION.
Page 5 of 6 STP24-0253 Estimate of Costs-Site Civil Works-Rev A.xls
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Bill of Quantities.pdfRelated documentApplication case desk ↗
About this file
- File size
- 122 KB (small file)
- File type
No other editions are linked here.